Hasakah Wheat Digital Crop Survey
Add to watchlistA field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.
Budget (BAC)
Actual cost
64% of budget
Progress
Estimate at completion
+SYP 3.3M
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-02-05 | 2026-03-24 | +47 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-19 | 2026-07-11 | +83 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-08-07 | 2026-11-11 | +96 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-19 | 2026-12-21 | +63 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-30 | +30 days | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
63%Awaiting acceptance
10%Not handed in
27%Deliverable flow
Display options
| Project plan & baseline027-D1 | 5% | CRT-027-01 | Approved | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2025-12-30 | V1 | 3 of 3 |
| Monitoring & reporting027-D2 | 5% | CRT-027-02 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-02-05 | V1 | 3 of 3 |
| Business requirements027-D3 | 11% | CRT-027-03 | Approved | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-03-14 | V1 | 3 of 3 |
| Solution design027-D4 | 10% | CRT-027-04 | Approved | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-04-19 | V1 | 3 of 3 |
| Release 1027-D5 | 16% | CRT-027-05 | Approved | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-05-26 | V1 | 3 of 3 |
| Release 2027-D6 | 16% | CRT-027-06 | Approved | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-07-01 | V1 | 3 of 3 |
| Integrations027-D7 | 10% | — | Under review | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-08-07 | V1 | 1 of 3 |
| System testing027-D8 | 8% | — | Draft | Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-09-12 | V0 | 0 of 3 |
| User acceptance testing027-D9 | 7% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-10-19 | V0 | 0 of 3 |
| Training & change027-D10 | 6% | — | Draft | Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-11-24 | V0 | 0 of 3 |
| Go-live & handover027-D11 | 6% | — | Draft | Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy | Eng. Fadi Al-Droubi | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |