PRJ-2026-027At risk4ExecutionHybridIn progressDelivered by:Planning and Statistics Authority

Hasakah Wheat Digital Crop Survey

Add to watchlist

A field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.

Budget (BAC)

SYP 160M

Actual cost

SYP 102.9M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 163.3M

+SYP 3.3M

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Planning and Statistics Authority

Project charter

Hasakah Wheat Digital Crop Survey

APPROVEDV2Approved ⁦2025-10-31⁩

1Project identity

Required at this stage
Project name
Hasakah Wheat Digital Crop Survey
Project code
PRJ-2026-027
Project sponsor
Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.sy
Project manager
Mariam Al-ZoubiMariam Al-ZoubiDirector, Education & Rural Development ProjectsP-029mariam.alzoubi@psa.gov.sy
Project owner
Eng. Fadi Al-DroubiEng. Fadi Al-DroubiDirector General, Human Development ProjectsP-014fadi.aldroubi@psa.gov.sy
Portfolio & programme
Planning, Statistics & Capability PortfolioPlanning, Statistics & Capability Programme
Type & methodology
Digital · Hybrid
Current phase
4Execution

2Background & rationale

Required at this stage

A field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.

3Objectives

Required at this stage
  1. 1Strengthen food security and revive wheat farming
  2. 2Reliable statistics and economic data for decisions

4Scope

Required at this stage

In scope

  • A field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.
  • Identity checks against the civil registry
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Identity checks against the civil registry
  2. 2Integration with internal systems
  3. 3Accessibility and UX standards

6Deliverables

Required at this stage
1Project management plan⁦2025-11-19⁩
2Main deliverable — stage 1⁦2026-06-07⁩
3Main deliverable — final stage⁦2026-11-02⁩
4Final report⁦2026-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-10-31⁩
  2. Contract signed⁦2026-01-09⁩
  3. 50% of works complete⁦2026-06-07⁩
  4. Provisional acceptance⁦2026-11-27⁩
  5. Closure⁦2026-12-31⁩

8Budget

Required at this stage
  • Main contract⁦71.9%⁩SYP115M
  • Supervision & consulting⁦14.1%⁩SYP22.5M
  • Internal team⁦9.4%⁩SYP15M
  • Contingency reserve (⁦5%⁩)⁦4.7%⁩SYP7.5M
The delivering body’s investment-plan allocationsTotalSYP160M

9Timeline

Required at this stage
Start
2025-11-022 November 2025
Baseline finish
2026-12-3131 December 2026
Duration
⁦14⁩ months

10Key risks

Required at this stage
  • MediumField enumerators covering too little of the wheat area

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the unified contracts law (⁦Law 51 of 2004⁩)

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • National Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • Project Approval CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly
Version V2 · ⁦4⁩ of ⁦4⁩ signaturesInternal — not for circulation outside the Authority