PRJ-2026-027At risk4ExecutionHybridIn progressDelivered by:Planning and Statistics Authority

Hasakah Wheat Digital Crop Survey

Add to watchlist

A field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.

Budget (BAC)

SYP 160M

Actual cost

SYP 102.9M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 163.3M

+SYP 3.3M

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SYP 160M split into spent, committed and left, with the estimate at completion

Forecast overrun SYP 3.3M
EAC SYP 163.3M
Revised request SYP 160M
  • Actual spendSYP 102.9M
  • Committed, not spentSYP 34.6M
  • Allotted, uncommittedSYP 17.7M
  • Contingency availableSYP 4.8M

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SYP 157.5M
Original budgetwhen the first baseline was approved
SYP 160M
Approved budgetafter approved change requests
SYP 160M
Current budgetavailable to spend now
SYP 160M
Revised budgetif the pending changes are approved
SYP 160M

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SYP 137.5M
Contracts1 active contract
SYP 122.5M
Purchase orders⁦1⁩ order
SYP 15M
Remaining budgetapproved less actual
SYP 57.1M

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SYP 102.9M
Accrualswork done, not yet invoiced
SYP 4.1M
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SYP 163.3M
ContingencySYP 3.2M drawn of SYP 8M
SYP 4.8M

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSYP 157.5M
ApprovedSYP 160M
Estimate at completionSYP 163.3M
Approved is SYP 2.5M (⁦1.6%⁩) above the estimate
The estimate at completion is SYP 5.8M (⁦3.7%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-08-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51027
  • WBS elements⁦5⁩ elements · P-2026-027.01 …
  • Purchase orders⁦1⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦6⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SYP 3.2M drawn of SYP 8M

  • Covering realised delivery risks⁦2026-08-29⁩SYP 3.2M

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSYP MCommittedSYP MActualSYP MEACSYP MVarianceSYP MConsumption
1Management & governance12.4213.0613.0613.06⁦−0.65⁩
2Analysis & design26.3827.7627.7627.76⁦−1.37⁩
3Build62.0862.0762.0462.08⁦−0.00⁩
4Testing & acceptance31.0419.780.0033.12⁦−2.08⁩
5Launch & handover23.2814.840.0024.84⁦−1.56⁩
Unallocated contingency4.800.000.002.40⁦+2.40⁩
Total160.00137.50102.86163.27⁦−3.27⁩

Budget split

WBS

SYP 160M

Budget

  • Management & governanceSYP 12.4M⁦8%⁩
  • Analysis & designSYP 26.4M⁦16%⁩
  • BuildSYP 62.1M⁦39%⁩
  • Testing & acceptanceSYP 31M⁦19%⁩
  • Launch & handoverSYP 23.3M⁦15%⁩
  • Unallocated contingencySYP 4.8M⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SYP millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-07-13⁩+194

SPI(t) ⁦0.69⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SYP 151.1M
The value of the work that should be done by today.
PV
Earned valueEV
SYP 100.8M
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SYP 102.9M
What has actually been spent on the work done.
AC
Budget at completionBAC
SYP 160M
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−2.06⁩ SYP M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−50.34⁩ SYP M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.98
Value produced per pound spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.67
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SYP 163.3M
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SYP 60.4M
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−3.27⁩ SYP M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.04
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSYP 163.3M
  • If the rest goes to planSYP 162.1M
  • At cost and schedule performanceSYP 193.4M
  • The PM’s bottom-up estimateSYP 163.3M
  • To stay within SYP 160M, cost performance on the rest must rise to ⁦1.04⁩ — above what has been achieved.

Estimate at completion at that performance

SYP 163.3M

Variance at completion: ⁦−3.27⁩ SYP M