Project status card
28 October 2026
Hasakah Wheat Digital Crop Survey
PRJ-2026-027 · Development Projects Follow-up Sector · Strategic · WP-2025-027
- Progress
- 63% / 72%
- SPI · CPI
- 0.88 · 0.98
- Spend
- SYP 102.9M / SYP 160M
- Estimate at completion
- SYP 163.3M
Schedule
Planned to date 72%
Forecast finish: 2027-01-31 · 31 days late
SPI0.88Schedule performance index · 0.88CPI0.98Cost performance index · 0.98Health dimensions
Last update: 2026-09-24 · Update overdue
Deliverables
5 of 9 due deliverables accepted on time (56%)
Next milestones
- Build complete2026-11-11
- Testing & acceptance complete2026-12-21
- Final handover2027-01-30
Top risks
- Field enumerators covering too little of the wheat area9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SYP 160M: 0 on track and 0 red or critical. Weighted progress is 63% against 72% planned, spend SYP 102.9M, and EAC SYP 163.3M (SYP 3.3M over).
1 project is more than a month behind baseline; the worst: Hasakah Wheat Digital Crop Survey (31 days).