PRJ-2026-001 · From item 2
Integrated Public Financial Management System — Phase 1Planned to date 74%
- SPI
- 0.82
- Forecast finish
- 2027-02-27
- Budget
- SYP 1.6B
58 days lateMaterial risks: 1Open impediments: 2Corrective plan CP-2026-05
October gate reviews.
Held on
14 October 202611:00 – 12:35
80 of 90 min
Approve the previous minutes
ApprovalDr. Reem Al-Qabbani
5 min
Public financial management system planning gate
DecisionNour Al-Jabiri
45 min
Earlier gate conditions — follow-up
For informationNizar Abu Fakhr
30 min
Approved and locked
1. Approve the previous minutes
Approved.
2. Public financial management system planning gate
PRJ-2026-001Sent back: the schedule ignores the ministries’ payroll integration delay.
3. Earlier gate conditions — follow-up
7 of 9 conditions met.
Voting rule: Simple majority; the chair holds the casting vote
Public financial management system plan sent back for rework
DEC-2026-038Rework
For 5Against 1Abstain 1Carried
Nour Al-Jabiri, as the project’s owner, objected and asked for two weeks.
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Quorum: Four of eight members, including the chair or vice-chair
At least 4 voting members needed
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-001 · From item 2
Integrated Public Financial Management System — Phase 1Planned to date 74%
58 days lateMaterial risks: 1Open impediments: 2Corrective plan CP-2026-05
Agenda item needing a decision · PRJ-2026-001
Public financial management system planning gateFrom item 2
Change request awaiting decision · CR-2026-008
Increase the customisation & integration budgetIntegrated Public Financial Management System — Phase 1
CP-2026-05 · Integrated Public Financial Management System — Phase 1
FundingSYP 170M· Asked from: Authority Executive Council
More customisation & integration allocation through change request CR-2026-008
Nothing