Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Knowledge base

Procedures, guidelines, policies and best practices.

What are you looking for?

One search across ⁦17⁩ articles, ⁦21⁩ lessons, ⁦8⁩ templates and ⁦25⁩ documents

Try:

Shelves

Pick a shelf to see its articles, or go to templates and lessons.

PMO picks

What any project manager needs before starting.

AI insight

Three projects enter tendering this quarter

The Deir ez-Zor suspension bridge, the Baniyas pilot desalination plant and the unified government contact centre are close to tender; on similar projects, contractor capacity and the funding model failed most.

Confidence⁦81%⁩

Most read

Recently revised

Due for review

Before year end

My saved

Articles you saved for later

Nothing saved yet. Open any article and press «Save».

Raising a change request and taking it to the change board

KB-101 · Procedures · 6 min read

Who raises it, how its cost, schedule and scope impact is measured, and when it reaches the change committee.

Owner: Dr. Ziad Al-Atassi·Updated 2026-09-14·Review by 2027-03-14

When a change request is needed

Any change to the approved baseline in scope, schedule or cost, ⁦or anything above 2% of the contract value⁩.

Steps

  1. 1The PM raises the request from the change requests page with its justification
  2. 2The project office measures cost, ⁦schedule and risk impact within 5 working days⁩
  3. 3It is put on the next change committee agenda
  4. 4The baseline is updated once the decision is approved

Approval limits

⁦Up to SYP 12⁩.⁦5M⁩: programme manager. Up to SYP ⁦500M⁩: the change committee. ⁦Up to SYP 1⁩.⁦25bn⁩: the National Projects Steering Committee. Above: the Authority Executive Council.

Sources

Was this article useful?

Change · Governance