Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Loose scope in design-build contracts breeds claims

LL-2026-007 · Contracts · High impact · Published

  1. 1ContextThe Hama National Hospital extension is a design-build contract.
  2. 2What happenedThe contractor claimed SYP ⁦350M for requirements added after concept design⁩: extra intensive-care wards and a revised HVAC system.
  3. 3ImpactClaims referred to the dispute committee; the extension decision deferred.

Recommendation

Freeze the building’s functional programme with the ministry that will use it before the proposal goes to committee.

Captured by
Eng. Sara Al-Barazi
Date
2026-09-08
Applies to
Construction