Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Nominate participants early in capability programmes

LL-2026-029 · Stakeholders · Low impact · Published

  1. 1ContextThe e-learning platform and computer labs for Raqqa schools.
  2. 2What happenedThe first cohort of teacher nominations slipped six weeks because the governorate education directorate was unclear on the selection criteria.
  3. 3ImpactThe first cohort moved to the next quarter.

Recommendation

Put the nomination criteria and per-programme and per-body quotas in the proposal itself.

Captured by
Mariam Al-Zoubi
Date
2026-02-26
Applies to
Consulting · Service