Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦4⁩ — April 2026

Maarat al-Numan roads, water & drainage — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
4
Date
⁦2026-04-22⁩
Reference
PAY-2025-025-04

Interim payment certificate no. (⁦4⁩)

For the work of April 2026

Contract number
PSA/2025/025
Tender file no.
2504860719
Contract
Maarat al-Numan roads, water & drainage — rehabilitation works
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
SYP4,900,000,000
Current contract value
SYP4,900,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date1,133,000,000
2Less: previous certificates(765,500,000)
3Value of work in this certificate367,500,000
4Less: retention (⁦10%⁩)(36,750,000)
5Less: advance payment recovery (⁦10%⁩)(36,750,000)
6Less: delay and breach penalties0
7Total deductions(73,500,000)
8Net amount payable to the contractorSYP294,000,000

Amount in words: Two hundred ninety-four million Syrian pounds only

Retention held up to this certificate: SYP 113.3M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation343,000,000127,525,00055,450,000182,975,000⁦53%⁩
Earthworks & foundations882,000,000197,375,00088,150,000285,525,000⁦32%⁩
Concrete & structural works1,519,000,000260,600,000125,750,000386,350,000⁦25%⁩
Mechanical, electrical & plumbing1,176,000,000124,125,00066,225,000190,350,000⁦16%⁩
Finishes & external works735,000,00048,800,00027,675,00076,475,000⁦10%⁩
Testing & commissioning245,000,0007,075,0004,250,00011,325,000⁦5%⁩
Total4,900,000,000765,500,000367,500,0001,133,000,000⁦23%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2026-04-22⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-04-24⁩

Project manager

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-04-27⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-04-30⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-05-03⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-04-22⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2026-04-24⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-04-27⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 3 days

  4. Payment order prepared⁦2026-04-30⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-05-03⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeLate · ⁦2026-09-24⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Wael Al-Khawlani → Dr. Samer Al-Daqqar

Certificate history

3 May 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-05-03 13:00

30 April 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-04-30 13:00

27 April 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Project manager certifies”

    2026-04-27 13:00

24 April 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-04-24 13:00

22 April 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-04-22 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close