Certificate ⁦2⁩ — November 2025

Maarat al-Numan roads, water & drainage — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
2
Date
⁦2025-11-28⁩
Reference
PAY-2025-025-02

Interim payment certificate no. (⁦2⁩)

For the work of November 2025

Contract number
PSA/2025/025
Tender file no.
2504860719
Contract
Maarat al-Numan roads, water & drainage — rehabilitation works
Contractor
Al-Bunyan Al-Mateen Contracting Co.
Contractor tax number
TX-403137
Project
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate
Contract period
⁦2025-08-03⁩ — ⁦2027-08-31⁩
Original contract value
SYP4,900,000,000
Current contract value
SYP4,900,000,000
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date458,000,000
2Less: previous certificates(159,750,000)
3Value of work in this certificate298,250,000
4Less: retention (⁦10%⁩)(29,825,000)
5Less: advance payment recovery (⁦10%⁩)(29,825,000)
6Less: delay and breach penalties0
7Total deductions(59,650,000)
8Net amount payable to the contractorSYP238,600,000

Amount in words: Two hundred thirty-eight million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 45.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation343,000,00026,925,00047,025,00073,950,000⁦22%⁩
Earthworks & foundations882,000,00041,575,00073,850,000115,425,000⁦13%⁩
Concrete & structural works1,519,000,00054,350,000101,825,000156,175,000⁦10%⁩
Mechanical, electrical & plumbing1,176,000,00025,525,00051,425,00076,950,000⁦7%⁩
Finishes & external works735,000,0009,950,00020,975,00030,925,000⁦4%⁩
Testing & commissioning245,000,0001,425,0003,150,0004,575,000⁦2%⁩
Total4,900,000,000159,750,000298,250,000458,000,000⁦9%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Anas Al-Sheikh

Al-Sheikh⁦2025-11-28⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-11-30⁩

Project manager

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-12-03⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2025-12-06⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2025-12-09⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-11-28⁩

    Eng. Anas Al-Sheikh

  2. Engineer verifies quantities⁦2025-11-30⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-12-03⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 3 days

  4. Payment order prepared⁦2025-12-06⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2025-12-09⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2026-03-03⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2026-08-04⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Wael Al-Khawlani → Dr. Samer Al-Daqqar

Certificate history

9 December 2025

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2025-12-09 13:00

6 December 2025

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2025-12-06 13:00

3 December 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Project manager certifies”

    2025-12-03 13:00

30 November 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-11-30 13:00

28 November 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-11-28 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close