Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 10
- Date
- 2026-10-06
- Reference
- PAY-2026-014
Interim payment certificate no. (10)
For the work of September 2026
- Contract number
- PSA/2025/005
- Tender file no.
- 2503460459
- Contract
- Qalamoun solar field — PV supply & installation
- Contractor
- Alternative Energy Contracting Est.
- Contractor tax number
- TX-434507
- Project
- 20 MW Qalamoun Solar Field
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- SYP2,025,000,000
- Current contract value
- SYP2,025,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 1,107,500,000 |
| 2 | Less: previous certificates | (1,002,500,000) |
| 3 | Value of work in this certificate | 105,000,000 |
| 4 | Less: retention (10%) | (10,500,000) |
| 5 | Less: advance payment recovery (10%) | (10,500,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (21,000,000) |
| 8 | Net amount payable to the contractor | SYP84,000,000 |
Amount in words: Eighty-four million Syrian pounds only
Retention held up to this certificate: SYP 110.8M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 141,750,000 | 131,150,000 | 10,600,000 | 141,750,000 | 100% |
| Earthworks & foundations | 364,500,000 | 290,950,000 | 25,275,000 | 316,225,000 | 87% |
| Concrete & structural works | 627,750,000 | 341,525,000 | 36,125,000 | 377,650,000 | 60% |
| Mechanical, electrical & plumbing | 486,000,000 | 164,350,000 | 21,700,000 | 186,050,000 | 38% |
| Finishes & external works | 303,750,000 | 65,050,000 | 9,700,000 | 74,750,000 | 25% |
| Testing & commissioning | 101,250,000 | 9,475,000 | 1,600,000 | 11,075,000 | 11% |
| Total | 2,025,000,000 | 1,002,500,000 | 105,000,000 | 1,107,500,000 | 55% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Hassan Al-Jubouri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Rami Youssef
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar