Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 6
- Date
- 2026-03-11
- Reference
- PAY-2025-005-06
Interim payment certificate no. (6)
For the work of February 2026
- Contract number
- PSA/2025/005
- Tender file no.
- 2503460459
- Contract
- Qalamoun solar field — PV supply & installation
- Contractor
- Alternative Energy Contracting Est.
- Contractor tax number
- TX-434507
- Project
- 20 MW Qalamoun Solar Field
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- SYP2,025,000,000
- Current contract value
- SYP2,025,000,000
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 715,000,000 |
| 2 | Less: previous certificates | (583,750,000) |
| 3 | Value of work in this certificate | 131,250,000 |
| 4 | Less: retention (10%) | (13,125,000) |
| 5 | Less: advance payment recovery (10%) | (13,125,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (26,250,000) |
| 8 | Net amount payable to the contractor | SYP105,000,000 |
Amount in words: One hundred five million Syrian pounds only
Retention held up to this certificate: SYP 71.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 141,750,000 | 96,625,000 | 18,825,000 | 115,450,000 | 81% |
| Earthworks & foundations | 364,500,000 | 149,825,000 | 30,350,000 | 180,175,000 | 49% |
| Concrete & structural works | 627,750,000 | 198,800,000 | 45,025,000 | 243,825,000 | 39% |
| Mechanical, electrical & plumbing | 486,000,000 | 95,350,000 | 24,775,000 | 120,125,000 | 25% |
| Finishes & external works | 303,750,000 | 37,675,000 | 10,600,000 | 48,275,000 | 16% |
| Testing & commissioning | 101,250,000 | 5,475,000 | 1,675,000 | 7,150,000 | 7% |
| Total | 2,025,000,000 | 583,750,000 | 131,250,000 | 715,000,000 | 35% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Hassan Al-Jubouri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Rami Youssef
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar