Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 8
- Date
- 2026-07-07
- Reference
- PAY-2025-005-08
Interim payment certificate no. (8)
For the work of June 2026
- Contract number
- PSA/2025/005
- Tender file no.
- 2503460459
- Contract
- Qalamoun solar field — PV supply & installation
- Contractor
- Alternative Energy Contracting Est.
- Contractor tax number
- TX-434507
- Project
- 20 MW Qalamoun Solar Field
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- SYP2,025,000,000
- Current contract value
- SYP2,025,000,000
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 945,250,000 |
| 2 | Less: previous certificates | (852,750,000) |
| 3 | Value of work in this certificate | 92,500,000 |
| 4 | Less: retention (10%) | (9,250,000) |
| 5 | Less: advance payment recovery (10%) | (9,250,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (18,500,000) |
| 8 | Net amount payable to the contractor | SYP74,000,000 |
Amount in words: Seventy-four million Syrian pounds only
Retention held up to this certificate: SYP 94.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 141,750,000 | 130,175,000 | 11,575,000 | 141,750,000 | 100% |
| Earthworks & foundations | 364,500,000 | 227,725,000 | 21,400,000 | 249,125,000 | 68% |
| Concrete & structural works | 627,750,000 | 290,525,000 | 31,800,000 | 322,325,000 | 51% |
| Mechanical, electrical & plumbing | 486,000,000 | 140,450,000 | 18,350,000 | 158,800,000 | 33% |
| Finishes & external works | 303,750,000 | 55,750,000 | 8,050,000 | 63,800,000 | 21% |
| Testing & commissioning | 101,250,000 | 8,125,000 | 1,325,000 | 9,450,000 | 9% |
| Total | 2,025,000,000 | 852,750,000 | 92,500,000 | 945,250,000 | 47% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Hassan Al-Jubouri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Rami Youssef
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar