PSA/2024/021
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
41% of the current value paid
Paid
SYP115Mof a current value of SYP 280M
Value of each certificate
The last 14 — gross and net
Approved: 16
Count: 16 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 16September 2026 | 2026-10-06 | SYP3.5M | SYP175K | SYP0 | SYP3.3M | Approved | |
| Certificate 15August 2026 | 2026-08-21 | SYP5M | SYP250K | SYP0 | SYP4.8M | Approved | |
| Certificate 14June 2026 | 2026-07-06 | SYP5.5M | SYP275K | SYP0 | SYP5.2M | Approved | |
| Certificate 13May 2026 | 2026-05-21 | SYP7.5M | SYP375K | SYP0 | SYP7.1M | Approved | |
| Certificate 12March 2026 | 2026-04-05 | SYP8.3M | SYP412.5K | SYP0 | SYP7.8M | Approved | |
| Certificate 11January 2026 | 2026-02-18 | SYP8.3M | SYP412.5K | SYP0 | SYP7.8M | Approved | |
| Certificate 10December 2025 | 2026-01-03 | SYP10.5M | SYP525K | SYP0 | SYP10M | Approved | |
| Certificate 9October 2025 | 2025-11-18 | SYP9.3M | SYP462.5K | SYP0 | SYP8.8M | Approved | |
| Certificate 8September 2025 | 2025-10-03 | SYP9.3M | SYP462.5K | SYP0 | SYP8.8M | Approved | |
| Certificate 7July 2025 | 2025-08-18 | SYP10.5M | SYP525K | SYP0 | SYP10M | Approved | |
| Certificate 6June 2025 | 2025-07-03 | SYP8M | SYP400K | SYP0 | SYP7.6M | Approved | |
| Certificate 5April 2025 | 2025-05-18 | SYP8.3M | SYP412.5K | SYP0 | SYP7.8M | Approved | |
| Certificate 4March 2025 | 2025-04-02 | SYP7.5M | SYP375K | SYP0 | SYP7.1M | Approved | |
| Certificate 3January 2025 | 2025-02-15 | SYP5.5M | SYP275K | SYP0 | SYP5.2M | Approved | |
| Certificate 2December 2024 | 2024-12-31 | SYP5M | SYP250K | SYP0 | SYP4.8M | Approved | |
| Certificate 1October 2024 | 2024-11-15 | SYP3.3M | SYP162.5K | SYP0 | SYP3.1M | Approved |