Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 8
- Date
- 2025-10-03
- Reference
- PAY-2024-021-08
Interim payment certificate no. (8)
For the work of September 2025
- Contract number
- PSA/2024/021
- Tender file no.
- 2402480277
- Contract
- Supervision — Sheikh Najjar industrial city rehabilitation
- Contractor
- Dar Al-Khibra Engineering Consultants
- Contractor tax number
- TX-418822
- Project
- Sheikh Najjar Industrial City Rehabilitation
- Contract period
- 2024-10-01 — 2027-06-30
- Original contract value
- SYP280,000,000
- Current contract value
- SYP280,000,000
- Linked milestone
- Mid-term review · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 57,250,000 |
| 2 | Less: previous certificates | (48,000,000) |
| 3 | Value of work in this certificate | 9,250,000 |
| 4 | Less: retention (5%) | (462,500) |
| 5 | Less: advance payment recovery (0%) | 0 |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (462,500) |
| 8 | Net amount payable to the contractor | SYP8,787,500 |
Amount in words: Eight million seven hundred eighty-seven thousand five hundred Syrian pounds only
Retention held up to this certificate: SYP 2.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Resident engineering staff | 173,600,000 | 29,950,000 | 5,775,000 | 35,725,000 | 21% |
| Visiting specialists | 50,400,000 | 8,625,000 | 1,675,000 | 10,300,000 | 20% |
| Laboratory & testing | 33,600,000 | 5,175,000 | 1,000,000 | 6,175,000 | 18% |
| Reporting & technical office | 22,400,000 | 4,250,000 | 800,000 | 5,050,000 | 23% |
| Total | 280,000,000 | 48,000,000 | 9,250,000 | 57,250,000 | 20% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Nabil Al-Khalil
Supervising engineer
Huda Al-Dandal
Project manager
Eng. Youssef Shehabi
Finance & contracts
Omar Al-Nahhas
Final approver
Rasha Al-Mudarres