Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 20
- Date
- 2026-04-19
- Reference
- PAY-2024-006-20
Interim payment certificate no. (20)
For the work of March 2026
- Contract number
- PSA/2024/006
- Tender file no.
- 2401430082
- Contract
- Hama National Hospital extension — civil & MEP works
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Hama National Hospital Upgrade & Extension
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- SYP14,000,000,000
- Current contract value
- SYP14,600,000,000including variations of SYP 600M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 8,344,750,000 |
| 2 | Less: previous certificates | (8,031,000,000) |
| 3 | Value of work in this certificate | 313,750,000 |
| 4 | Less: retention (10%) | (31,375,000) |
| 5 | Less: advance payment recovery (10%) | (31,375,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (62,750,000) |
| 8 | Net amount payable to the contractor | SYP251,000,000 |
Amount in words: Two hundred fifty-one million Syrian pounds only
Retention held up to this certificate: SYP 834.5M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,022,000,000 | 992,325,000 | 29,675,000 | 1,022,000,000 | 100% |
| Earthworks & foundations | 2,628,000,000 | 2,352,625,000 | 75,925,000 | 2,428,550,000 | 92% |
| Concrete & structural works | 4,526,000,000 | 2,737,525,000 | 108,025,000 | 2,845,550,000 | 63% |
| Mechanical, electrical & plumbing | 3,504,000,000 | 1,336,175,000 | 65,750,000 | 1,401,925,000 | 40% |
| Finishes & external works | 2,190,000,000 | 533,725,000 | 29,550,000 | 563,275,000 | 26% |
| Testing & commissioning | 730,000,000 | 78,625,000 | 4,825,000 | 83,450,000 | 11% |
| Total | 14,600,000,000 | 8,031,000,000 | 313,750,000 | 8,344,750,000 | 57% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Sara Al-Barazi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar