Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦21⁩ — May 2026

Hama National Hospital extension — civil & MEP works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
21
Date
⁦2026-05-27⁩
Reference
PAY-2024-006-21

Interim payment certificate no. (⁦21⁩)

For the work of May 2026

Contract number
PSA/2024/006
Tender file no.
2401430082
Contract
Hama National Hospital extension — civil & MEP works
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Hama National Hospital Upgrade & Extension
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
SYP14,000,000,000
Current contract value
SYP14,600,000,000including variations of SYP 600M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date8,634,500,000
2Less: previous certificates(8,344,750,000)
3Value of work in this certificate289,750,000
4Less: retention (⁦10%⁩)(28,975,000)
5Less: advance payment recovery (⁦10%⁩)(28,975,000)
6Less: delay and breach penalties0
7Total deductions(57,950,000)
8Net amount payable to the contractorSYP231,800,000

Amount in words: Two hundred thirty-one million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 863.5M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,022,000,000996,000,00026,000,0001,022,000,000⁦100%⁩
Earthworks & foundations2,628,000,0002,478,125,00070,225,0002,548,350,000⁦97%⁩
Concrete & structural works4,526,000,0002,844,575,00099,800,0002,944,375,000⁦65%⁩
Mechanical, electrical & plumbing3,504,000,0001,389,200,00061,400,0001,450,600,000⁦41%⁩
Finishes & external works2,190,000,000555,075,00027,750,000582,825,000⁦27%⁩
Testing & commissioning730,000,00081,775,0004,575,00086,350,000⁦12%⁩
Total14,600,000,0008,344,750,000289,750,0008,634,500,000⁦59%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2026-05-27⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-05-29⁩

Project manager

Eng. Sara Al-Barazi

Al-Barazi⁦2026-06-01⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-06-04⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-06-07⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-05-27⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2026-05-29⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-06-01⁩

    Eng. Sara Al-Barazi · Senior Project Manager — Hospitals & Health Facilities

    Took 3 days

  4. Payment order prepared⁦2026-06-04⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-06-07⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-05-18⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Sara Al-Barazi → Dr. Samer Al-Daqqar

Certificate history

7 June 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-06-07 13:00

4 June 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-06-04 13:00

1 June 2026

  1. Approval: Eng. Sara Al-Barazi signed “Project manager certifies”

    2026-06-01 13:00

29 May 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-05-29 13:00

27 May 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-05-27 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close