Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 19
- Date
- 2026-03-11
- Reference
- PAY-2024-006-19
Interim payment certificate no. (19)
For the work of February 2026
- Contract number
- PSA/2024/006
- Tender file no.
- 2401430082
- Contract
- Hama National Hospital extension — civil & MEP works
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Hama National Hospital Upgrade & Extension
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- SYP14,000,000,000
- Current contract value
- SYP14,600,000,000including variations of SYP 600M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 8,031,000,000 |
| 2 | Less: previous certificates | (7,681,500,000) |
| 3 | Value of work in this certificate | 349,500,000 |
| 4 | Less: retention (10%) | (34,950,000) |
| 5 | Less: advance payment recovery (10%) | (34,950,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (69,900,000) |
| 8 | Net amount payable to the contractor | SYP279,600,000 |
Amount in words: Two hundred seventy-nine million six hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 803.1M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,022,000,000 | 987,025,000 | 34,975,000 | 1,022,000,000 | 100% |
| Earthworks & foundations | 2,628,000,000 | 2,214,600,000 | 84,225,000 | 2,298,825,000 | 87% |
| Concrete & structural works | 4,526,000,000 | 2,618,275,000 | 120,300,000 | 2,738,575,000 | 61% |
| Mechanical, electrical & plumbing | 3,504,000,000 | 1,276,825,000 | 72,375,000 | 1,349,200,000 | 39% |
| Finishes & external works | 2,190,000,000 | 509,725,000 | 32,375,000 | 542,100,000 | 25% |
| Testing & commissioning | 730,000,000 | 75,050,000 | 5,250,000 | 80,300,000 | 11% |
| Total | 14,600,000,000 | 7,681,500,000 | 349,500,000 | 8,031,000,000 | 55% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Sara Al-Barazi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar