Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦19⁩ — February 2026

Hama National Hospital extension — civil & MEP works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
19
Date
⁦2026-03-11⁩
Reference
PAY-2024-006-19

Interim payment certificate no. (⁦19⁩)

For the work of February 2026

Contract number
PSA/2024/006
Tender file no.
2401430082
Contract
Hama National Hospital extension — civil & MEP works
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Hama National Hospital Upgrade & Extension
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
SYP14,000,000,000
Current contract value
SYP14,600,000,000including variations of SYP 600M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date8,031,000,000
2Less: previous certificates(7,681,500,000)
3Value of work in this certificate349,500,000
4Less: retention (⁦10%⁩)(34,950,000)
5Less: advance payment recovery (⁦10%⁩)(34,950,000)
6Less: delay and breach penalties0
7Total deductions(69,900,000)
8Net amount payable to the contractorSYP279,600,000

Amount in words: Two hundred seventy-nine million six hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 803.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,022,000,000987,025,00034,975,0001,022,000,000⁦100%⁩
Earthworks & foundations2,628,000,0002,214,600,00084,225,0002,298,825,000⁦87%⁩
Concrete & structural works4,526,000,0002,618,275,000120,300,0002,738,575,000⁦61%⁩
Mechanical, electrical & plumbing3,504,000,0001,276,825,00072,375,0001,349,200,000⁦39%⁩
Finishes & external works2,190,000,000509,725,00032,375,000542,100,000⁦25%⁩
Testing & commissioning730,000,00075,050,0005,250,00080,300,000⁦11%⁩
Total14,600,000,0007,681,500,000349,500,0008,031,000,000⁦55%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2026-03-11⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-03-13⁩

Project manager

Eng. Sara Al-Barazi

Al-Barazi⁦2026-03-16⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-19⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-22⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-11⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2026-03-13⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-03-16⁩

    Eng. Sara Al-Barazi · Senior Project Manager — Hospitals & Health Facilities

    Took 3 days

  4. Payment order prepared⁦2026-03-19⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-22⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-05-18⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Sara Al-Barazi → Dr. Samer Al-Daqqar

Certificate history

22 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-22 13:00

19 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-19 13:00

16 March 2026

  1. Approval: Eng. Sara Al-Barazi signed “Project manager certifies”

    2026-03-16 13:00

13 March 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-03-13 13:00

11 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-11 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close