Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 17
- Date
- 2025-12-24
- Reference
- PAY-2024-006-17
Interim payment certificate no. (17)
For the work of December 2025
- Contract number
- PSA/2024/006
- Tender file no.
- 2401430082
- Contract
- Hama National Hospital extension — civil & MEP works
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Hama National Hospital Upgrade & Extension
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- SYP14,000,000,000
- Current contract value
- SYP14,600,000,000including variations of SYP 600M
- Linked milestone
- MEP systems installed · MS-G4 Testing & acceptance complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 7,231,750,000 |
| 2 | Less: previous certificates | (6,821,250,000) |
| 3 | Value of work in this certificate | 410,500,000 |
| 4 | Less: retention (10%) | (41,050,000) |
| 5 | Less: advance payment recovery (10%) | (41,050,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (82,100,000) |
| 8 | Net amount payable to the contractor | SYP328,400,000 |
Amount in words: Three hundred twenty-eight million four hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 723.2M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,022,000,000 | 974,475,000 | 47,525,000 | 1,022,000,000 | 100% |
| Earthworks & foundations | 2,628,000,000 | 1,871,500,000 | 96,825,000 | 1,968,325,000 | 75% |
| Concrete & structural works | 4,526,000,000 | 2,324,850,000 | 141,175,000 | 2,466,025,000 | 54% |
| Mechanical, electrical & plumbing | 3,504,000,000 | 1,132,300,000 | 82,625,000 | 1,214,925,000 | 35% |
| Finishes & external works | 2,190,000,000 | 451,675,000 | 36,475,000 | 488,150,000 | 22% |
| Testing & commissioning | 730,000,000 | 66,450,000 | 5,875,000 | 72,325,000 | 10% |
| Total | 14,600,000,000 | 6,821,250,000 | 410,500,000 | 7,231,750,000 | 50% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Sara Al-Barazi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar