Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦17⁩ — December 2025

Hama National Hospital extension — civil & MEP works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
17
Date
⁦2025-12-24⁩
Reference
PAY-2024-006-17

Interim payment certificate no. (⁦17⁩)

For the work of December 2025

Contract number
PSA/2024/006
Tender file no.
2401430082
Contract
Hama National Hospital extension — civil & MEP works
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Hama National Hospital Upgrade & Extension
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
SYP14,000,000,000
Current contract value
SYP14,600,000,000including variations of SYP 600M
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SYP)

1Total value of work completed to date7,231,750,000
2Less: previous certificates(6,821,250,000)
3Value of work in this certificate410,500,000
4Less: retention (⁦10%⁩)(41,050,000)
5Less: advance payment recovery (⁦10%⁩)(41,050,000)
6Less: delay and breach penalties0
7Total deductions(82,100,000)
8Net amount payable to the contractorSYP328,400,000

Amount in words: Three hundred twenty-eight million four hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 723.2M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,022,000,000974,475,00047,525,0001,022,000,000⁦100%⁩
Earthworks & foundations2,628,000,0001,871,500,00096,825,0001,968,325,000⁦75%⁩
Concrete & structural works4,526,000,0002,324,850,000141,175,0002,466,025,000⁦54%⁩
Mechanical, electrical & plumbing3,504,000,0001,132,300,00082,625,0001,214,925,000⁦35%⁩
Finishes & external works2,190,000,000451,675,00036,475,000488,150,000⁦22%⁩
Testing & commissioning730,000,00066,450,0005,875,00072,325,000⁦10%⁩
Total14,600,000,0006,821,250,000410,500,0007,231,750,000⁦50%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2025-12-24⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2025-12-26⁩

Project manager

Eng. Sara Al-Barazi

Al-Barazi⁦2025-12-29⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-01-01⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-01-04⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2025-12-24⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2025-12-26⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2025-12-29⁩

    Eng. Sara Al-Barazi · Senior Project Manager — Hospitals & Health Facilities

    Took 3 days

  4. Payment order prepared⁦2026-01-01⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-01-04⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-05-18⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Sara Al-Barazi → Dr. Samer Al-Daqqar

Certificate history

4 January 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-01-04 13:00

1 January 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-01-01 13:00

29 December 2025

  1. Approval: Eng. Sara Al-Barazi signed “Project manager certifies”

    2025-12-29 13:00

26 December 2025

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2025-12-26 13:00

24 December 2025

  1. Approval: Contractor signed “Certificate submitted”

    2025-12-24 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close