Interim payment certificate no. (11)
For the work of April 2025
- Contract number
- PSA/2024/006
- Tender file no.
- 2401430082
- Contract
- Hama National Hospital extension — civil & MEP works
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Hama National Hospital Upgrade & Extension
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- SYP14,000,000,000
- Current contract value
- SYP14,600,000,000including variations of SYP 600M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 4,220,250,000 |
| 2 | Less: previous certificates | (3,738,000,000) |
| 3 | Value of work in this certificate | 482,250,000 |
| 4 | Less: retention (10%) | (48,225,000) |
| 5 | Less: advance payment recovery (10%) | (48,225,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (96,450,000) |
| 8 | Net amount payable to the contractor | SYP385,800,000 |
Amount in words: Three hundred eighty-five million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 422M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,022,000,000 | 610,400,000 | 71,175,000 | 681,575,000 | 67% |
| Earthworks & foundations | 2,628,000,000 | 949,675,000 | 113,825,000 | 1,063,500,000 | 40% |
| Concrete & structural works | 4,526,000,000 | 1,273,900,000 | 165,200,000 | 1,439,100,000 | 32% |
| Mechanical, electrical & plumbing | 3,504,000,000 | 620,275,000 | 88,725,000 | 709,000,000 | 20% |
| Finishes & external works | 2,190,000,000 | 247,375,000 | 37,500,000 | 284,875,000 | 13% |
| Testing & commissioning | 730,000,000 | 36,375,000 | 5,825,000 | 42,200,000 | 6% |
| Total | 14,600,000,000 | 3,738,000,000 | 482,250,000 | 4,220,250,000 | 29% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Sara Al-Barazi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar