Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦7⁩ — November 2024

Hama National Hospital extension — civil & MEP works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
7
Date
⁦2024-12-04⁩
Reference
PAY-2024-006-07

Interim payment certificate no. (⁦7⁩)

For the work of November 2024

Contract number
PSA/2024/006
Tender file no.
2401430082
Contract
Hama National Hospital extension — civil & MEP works
Contractor
Al-Fayhaa General Contracting Co.
Contractor tax number
TX-412548
Project
Hama National Hospital Upgrade & Extension
Contract period
⁦2024-03-03⁩ — ⁦2026-12-31⁩
Original contract value
SYP14,000,000,000
Current contract value
SYP14,600,000,000including variations of SYP 600M
Linked milestone
Earthworks & foundations complete · MS-G2 Designs approved

Certificate summary (SYP)

1Total value of work completed to date2,224,000,000
2Less: previous certificates(1,733,750,000)
3Value of work in this certificate490,250,000
4Less: retention (⁦10%⁩)(49,025,000)
5Less: advance payment recovery (⁦10%⁩)(49,025,000)
6Less: delay and breach penalties0
7Total deductions(98,050,000)
8Net amount payable to the contractorSYP392,200,000

Amount in words: Three hundred ninety-two million two hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 222.4M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation1,022,000,000283,200,00075,975,000359,175,000⁦35%⁩
Earthworks & foundations2,628,000,000440,600,000119,850,000560,450,000⁦21%⁩
Concrete & structural works4,526,000,000590,850,000167,525,000758,375,000⁦17%⁩
Mechanical, electrical & plumbing3,504,000,000287,575,00086,050,000373,625,000⁦11%⁩
Finishes & external works2,190,000,000114,675,00035,450,000150,125,000⁦7%⁩
Testing & commissioning730,000,00016,850,0005,400,00022,250,000⁦3%⁩
Total14,600,000,0001,733,750,000490,250,0002,224,000,000⁦15%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Walid Al-Masri

Al-Masri⁦2024-12-04⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2024-12-06⁩

Project manager

Eng. Sara Al-Barazi

Al-Barazi⁦2024-12-09⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2024-12-12⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2024-12-15⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2024-12-04⁩

    Eng. Walid Al-Masri

  2. Engineer verifies quantities⁦2024-12-06⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2024-12-09⁩

    Eng. Sara Al-Barazi · Senior Project Manager — Hospitals & Health Facilities

    Took 3 days

  4. Payment order prepared⁦2024-12-12⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2024-12-15⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneEarthworks & foundations completeDone · ⁦2024-12-17⁩
  2. Project milestoneMS-G2Designs approvedMilestone approved ⁦2025-09-29⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Sara Al-Barazi → Dr. Samer Al-Daqqar

Certificate history

15 December 2024

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2024-12-15 13:00

12 December 2024

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2024-12-12 13:00

9 December 2024

  1. Approval: Eng. Sara Al-Barazi signed “Project manager certifies”

    2024-12-09 13:00

6 December 2024

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2024-12-06 13:00

4 December 2024

  1. Approval: Contractor signed “Certificate submitted”

    2024-12-04 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close