Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 4
- Date
- 2024-08-11
- Reference
- PAY-2024-006-04
Interim payment certificate no. (4)
For the work of July 2024
- Contract number
- PSA/2024/006
- Tender file no.
- 2401430082
- Contract
- Hama National Hospital extension — civil & MEP works
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Hama National Hospital Upgrade & Extension
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- SYP14,000,000,000
- Current contract value
- SYP14,600,000,000including variations of SYP 600M
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SYP)
| 1 | Total value of work completed to date | 984,000,000 |
| 2 | Less: previous certificates | (646,750,000) |
| 3 | Value of work in this certificate | 337,250,000 |
| 4 | Less: retention (10%) | (33,725,000) |
| 5 | Less: advance payment recovery (10%) | (33,725,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (67,450,000) |
| 8 | Net amount payable to the contractor | SYP269,800,000 |
Amount in words: Two hundred sixty-nine million eight hundred thousand Syrian pounds only
Retention held up to this certificate: SYP 98.4M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,022,000,000 | 105,350,000 | 53,550,000 | 158,900,000 | 16% |
| Earthworks & foundations | 2,628,000,000 | 164,025,000 | 83,950,000 | 247,975,000 | 9% |
| Concrete & structural works | 4,526,000,000 | 220,450,000 | 115,100,000 | 335,550,000 | 7% |
| Mechanical, electrical & plumbing | 3,504,000,000 | 107,600,000 | 57,700,000 | 165,300,000 | 5% |
| Finishes & external works | 2,190,000,000 | 42,975,000 | 23,450,000 | 66,425,000 | 3% |
| Testing & commissioning | 730,000,000 | 6,350,000 | 3,500,000 | 9,850,000 | 1% |
| Total | 14,600,000,000 | 646,750,000 | 337,250,000 | 984,000,000 | 7% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Sara Al-Barazi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar