Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-027At risk4ExecutionHybridIn progressDelivered by:Planning and Statistics Authority

Hasakah Wheat Digital Crop Survey

Add to watchlist

A field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.

Budget (BAC)

SYP 160M

Actual cost

SYP 102.9M

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SYP 163.3M

+SYP 3.3M

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+30⁩ days vs approved

Baseline (original = approved)⁦2026-12-31⁩
Current forecast⁦2027-01-30⁩
By earned schedule⁦2027-07-13⁩
Critical activities
6
of ⁦8⁩ open activities
Late activities
5
past their baseline finish
Schedule performance
0.67
earned ÷ planned value
Next milestone
in 14 days
Build complete
Expand allCollapse all
Activity
Hasakah Wheat Digital Crop SurveyPlanned: ⁦2025-11-02⁩ → ⁦2026-12-31⁩Forecast: ⁦2025-11-02⁩ → ⁦2027-01-30⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-11-02⁩ → ⁦2026-02-05⁩Actual: ⁦2025-11-02⁩ → ⁦2026-03-24⁩
Project plan & baselinePlanned: ⁦2025-11-02⁩ → ⁦2025-12-30⁩Actual: ⁦2025-11-02⁩ → ⁦2026-01-28⁩
Monitoring & reportingPlanned: ⁦2025-12-09⁩ → ⁦2026-02-05⁩Actual: ⁦2025-12-27⁩ → ⁦2026-03-24⁩
Project plan approvedPlanned: ⁦2026-02-05⁩ → ⁦2026-02-05⁩Actual: ⁦2026-03-24⁩ → ⁦2026-03-24⁩Project plan approved
Analysis & designPlanned: ⁦2026-01-14⁩ → ⁦2026-04-19⁩Actual: ⁦2026-02-19⁩ → ⁦2026-07-11⁩
Business requirementsPlanned: ⁦2026-01-14⁩ → ⁦2026-03-14⁩Actual: ⁦2026-02-19⁩ → ⁦2026-05-18⁩
Solution designPlanned: ⁦2026-02-20⁩ → ⁦2026-04-19⁩Actual: ⁦2026-04-15⁩ → ⁦2026-07-11⁩
Designs approvedPlanned: ⁦2026-04-19⁩ → ⁦2026-04-19⁩Actual: ⁦2026-07-11⁩ → ⁦2026-07-11⁩Designs approved
BuildPlanned: ⁦2026-03-28⁩ → ⁦2026-08-07⁩Forecast: ⁦2026-06-08⁩ → ⁦2026-11-11⁩Float: ⁦0⁩d
Release 1Planned: ⁦2026-03-28⁩ → ⁦2026-05-26⁩Actual: ⁦2026-06-08⁩ → ⁦2026-09-04⁩
Release 2Planned: ⁦2026-05-04⁩ → ⁦2026-07-01⁩Actual: ⁦2026-08-02⁩ → ⁦2026-10-26⁩
IntegrationsPlanned: ⁦2026-06-09⁩ → ⁦2026-08-07⁩Forecast: ⁦2026-06-09⁩ → ⁦2026-11-11⁩Float: ⁦0⁩dDrag to change its duration+96
Build completePlanned: ⁦2026-08-07⁩ → ⁦2026-08-07⁩Forecast: ⁦2026-11-11⁩ → ⁦2026-11-11⁩Float: ⁦80⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2026-07-16⁩ → ⁦2026-10-19⁩Forecast: ⁦2026-10-30⁩ → ⁦2026-12-21⁩Float: ⁦0⁩d
System testingPlanned: ⁦2026-07-16⁩ → ⁦2026-09-12⁩Forecast: ⁦2026-10-30⁩ → ⁦2026-12-01⁩Float: ⁦0⁩dDrag to change its dates+80
User acceptance testingPlanned: ⁦2026-08-21⁩ → ⁦2026-10-19⁩Forecast: ⁦2026-11-19⁩ → ⁦2026-12-21⁩Float: ⁦0⁩dDrag to change its dates+63
Testing & acceptance completePlanned: ⁦2026-10-19⁩ → ⁦2026-10-19⁩Forecast: ⁦2026-12-21⁩ → ⁦2026-12-21⁩Float: ⁦40⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-09-27⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-09⁩ → ⁦2027-01-30⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-09-27⁩ → ⁦2026-11-24⁩Forecast: ⁦2026-12-09⁩ → ⁦2027-01-10⁩Float: ⁦0⁩dDrag to change its dates+47
Go-live & handoverPlanned: ⁦2026-11-03⁩ → ⁦2026-12-31⁩Forecast: ⁦2026-12-29⁩ → ⁦2027-01-30⁩Float: ⁦0⁩dDrag to change its dates+30
Final handoverPlanned: ⁦2026-12-31⁩ → ⁦2026-12-31⁩Forecast: ⁦2027-01-30⁩ → ⁦2027-01-30⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦8⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦5⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 64 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

47
83
96
63
30
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close