Proposal
Project proposal & feasibility study
Justification, objectives, benefits, cost and initial risks
- Form no.
- PSA-PMO-F01
- Template edition
- 2.1
- Version
- V2
- Form date
- 2025-04-06
Auto-filled — Filled by the platform from the project record, not typed.
- Project code
- PRJ-2026-027
- Project
- Hasakah Wheat Digital Crop Survey
- Portfolio
- Planning, Statistics & Capability Portfolio
- Sector
- Development Projects Follow-up Sector
- Sponsor
- Eng. Abdulrahman Al-Kilani
- Project manager
- Mariam Al-Zoubi
1The proposalAuto-filled
- TitleAuto-filled
- Hasakah Wheat Digital Crop Survey
- Proposed byAuto-filled
- Mariam Al-Zoubi
- DepartmentAuto-filled
- Education & Rural Development Projects Directorate
- Submitted onAuto-filled
- 2025-04-06
- Proposal numberAuto-filled
- DMD-2026-027
2Justification
A field survey with tablets and satellite imagery of the wheat area and expected yield in Al-Hasakah, with the Ministry of Agriculture, to plan grain reception and marketing.
3Objectives
- Strengthen food security and revive wheat farming
- Reliable statistics and economic data for decisions
Strategic objectives served
- SO-4.1 — Strengthen food security and revive wheat farming
- SO-1.2 — Reliable statistics and economic data for decisions
4Expected benefits
| Kind | Benefit |
|---|---|
| No benefits recorded yet | |
5Cost & feasibility
Estimated cost
SYP 160M
Funding
The delivering body’s investment-plan allocations
| Cost line | Amount |
|---|---|
| Main contract | SYP 115M |
| Supervision & consulting | SYP 22.5M |
| Internal team | SYP 15M |
| Contingency reserve (5%) | SYP 7.5M |
| Total | SYP 160M |
6Initial risks
| Risk | Level | Proposed response |
|---|---|---|
| Field enumerators covering too little of the wheat area | Medium | Treated in the risk management plan |
Approval logChain: Proposal & feasibility approval · version 4
Every decision on the form — who, their role, the note and the time. It prints with the form.
| # | Step | Kind | Name | Decision | Note | Date & time |
|---|---|---|---|---|---|---|
| 1 | Author | — | Mariam Al-ZoubiDirector, Education & Rural Development Projects | Submitted | — | 2025-04-06 11:20 |
| 2 | Line manager endorsement | Technical acceptance | Eng. Lina Al-AttarThe requester’s line manager | Approved | — | 2025-04-07 09:00 |
| 3 | PMO review | Methodology review | Mariam Al-ZoubiPMO — analyst | Approved | — | 2025-04-09 10:07 |
| 4 | Portfolio manager review | Technical acceptance | Dr. Reem Al-QabbaniPortfolio manager | Approved | Consistent with the portfolio plan and its priorities. | 2025-04-14 11:14 |
| 5 | Cost & funding review | Financial approval | Rasha Al-MudarresFinance | Approved | — | 2025-04-15 11:56 |
| 6 | Project Approval Committee | Technical acceptance | Approval engineProject Approval Committee | Pre-breach alert | — | 2025-04-21 08:00 |
| 7 | Project Approval Committee | Technical acceptance | Dr. Reem Al-QabbaniProject Approval Committee | Approved | — | 2025-04-22 13:28 |
Signatures
Line manager endorsement
Eng. Lina Al-Attar
Approved2025-04-07
PMO review
Mariam Al-Zoubi
Approved2025-04-09
Portfolio manager review
Dr. Reem Al-Qabbani
Approved2025-04-14
Cost & funding review
Rasha Al-Mudarres
Approved2025-04-15
Project Approval Committee
Dr. Reem Al-Qabbani
Approved2025-04-22