Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

National-system integration needs early link-up records

LL-2026-014 · Integration · High impact · Published

  1. 1ContextThe Unified Government e-Services Platform relies on the civil registry for identity checks, on the national interoperability framework to reach the ministries’ systems and on the banks for e-payment.
  2. 2What happened⁦Link-up records with the data-owning bodies slipped 11 weeks because they only started after the contract award⁩.
  3. 3ImpactA ⁦42-day slip to go-live and SYP⁩ ⁦90M of extra cost⁩.

Recommendation

Start link-up requests and their agreed time limits during feasibility, and plan a full integration sprint.

Captured by
Eng. Tarek Al-Mardini
Date
2026-10-06
Applies to
Digital · Service · IT