Warning of delay penalties

CompletedVery urgentConfidential

Outgoing Letter, dated 15 October 2026

Syrian Arab Republic

Planning and Statistics Authority

Incoming & Outgoing Mail

Number:
ص/2026/0403
Date:
⁦15 October 2026⁩
Attachments:
1

CONFIDENTIAL

Subject: Warning of delay penalties

Al-Fayhaa General Contracting Co.

Greetings,

With reference to contract PSA/⁦2024/006 for the Hama National Hospital extension⁩, and to the supervising consultant’s ⁦September report showing the structural works 96 days behind the approved programme⁩, the Authority will apply delay penalties under the general tender conditions and the contracts law (⁦Law 51 of 2004⁩) from the next payment certificate.

Please submit a revised programme and an acceleration plan within ten days.

With our kind regards,

Deputy President, Finance, Administration & the Investment Plan

Salma Al-Zaim

Copy to:

  • Legal Affairs
  • Al-Assi Project Management Group (supervising consultant)

Supervising consultant report — September