Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦17⁩ — August 2026

Supervision — Douma wastewater treatment plant

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
17
Date
⁦2026-08-21⁩
Reference
PAY-2024-018-17

Interim payment certificate no. (⁦17⁩)

For the work of August 2026

Contract number
PSA/2024/018
Tender file no.
2402270238
Contract
Supervision — Douma wastewater treatment plant
Contractor
Dar Al-Khibra Engineering Consultants
Contractor tax number
TX-418822
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-08-31⁩
Original contract value
SYP235,000,000
Current contract value
SYP235,000,000
Linked milestone
Supervision to provisional acceptance · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date115,000,000
2Less: previous certificates(111,250,000)
3Value of work in this certificate3,750,000
4Less: retention (⁦5%⁩)(187,500)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(187,500)
8Net amount payable to the contractorSYP3,562,500

Amount in words: Three million five hundred sixty-two thousand five hundred Syrian pounds only

Retention held up to this certificate: SYP 5.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff145,700,00069,400,0002,350,00071,750,000⁦49%⁩
Visiting specialists42,300,00020,025,000675,00020,700,000⁦49%⁩
Laboratory & testing28,200,00012,000,000425,00012,425,000⁦44%⁩
Reporting & technical office18,800,0009,825,000300,00010,125,000⁦54%⁩
Total235,000,000111,250,0003,750,000115,000,000⁦49%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Nabil Al-Khalil

Al-Khalil⁦2026-08-21⁩

Supervising engineer

Huda Al-Dandal

Al-Dandal⁦2026-08-23⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2026-08-26⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-08-29⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2026-09-01⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-08-21⁩

    Eng. Nabil Al-Khalil

  2. Engineer verifies quantities⁦2026-08-23⁩

    Huda Al-Dandal · Senior Financial Analyst — Investment Plan

    Took 2 days

  3. Project manager certifies⁦2026-08-26⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2026-08-29⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-01⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision to provisional acceptanceIn progress · ⁦2027-03-11⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderHuda Al-Dandal → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Rasha Al-Mudarres

Certificate history

1 September 2026

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2026-09-01 13:00

29 August 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-08-29 13:00

26 August 2026

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2026-08-26 13:00

23 August 2026

  1. Approval: Huda Al-Dandal signed “Engineer verifies quantities”

    2026-08-23 13:00

21 August 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-08-21 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close