Certificate ⁦13⁩ — January 2026

Supervision — Douma wastewater treatment plant

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
13
Date
⁦2026-02-18⁩
Reference
PAY-2024-018-13

Interim payment certificate no. (⁦13⁩)

For the work of January 2026

Contract number
PSA/2024/018
Tender file no.
2402270238
Contract
Supervision — Douma wastewater treatment plant
Contractor
Dar Al-Khibra Engineering Consultants
Contractor tax number
TX-418822
Project
Douma Wastewater Treatment Plant
Contract period
⁦2024-07-01⁩ — ⁦2027-08-31⁩
Original contract value
SYP235,000,000
Current contract value
SYP235,000,000
Linked milestone
Supervision to provisional acceptance · MS-G5 Final handover

Certificate summary (SYP)

1Total value of work completed to date93,250,000
2Less: previous certificates(85,000,000)
3Value of work in this certificate8,250,000
4Less: retention (⁦5%⁩)(412,500)
5Less: advance payment recovery (⁦0%⁩)0
6Less: delay and breach penalties0
7Total deductions(412,500)
8Net amount payable to the contractorSYP7,837,500

Amount in words: Seven million eight hundred thirty-seven thousand five hundred Syrian pounds only

Retention held up to this certificate: SYP 4.7M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Resident engineering staff145,700,00053,050,0005,150,00058,200,000⁦40%⁩
Visiting specialists42,300,00015,300,0001,475,00016,775,000⁦40%⁩
Laboratory & testing28,200,0009,150,000925,00010,075,000⁦36%⁩
Reporting & technical office18,800,0007,500,000700,0008,200,000⁦44%⁩
Total235,000,00085,000,0008,250,00093,250,000⁦40%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Nabil Al-Khalil

Al-Khalil⁦2026-02-18⁩

Supervising engineer

Huda Al-Dandal

Al-Dandal⁦2026-02-20⁩

Project manager

Eng. Qasem Al-Hariri

Al-Hariri⁦2026-02-23⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-02-26⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2026-03-01⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-02-18⁩

    Eng. Nabil Al-Khalil

  2. Engineer verifies quantities⁦2026-02-20⁩

    Huda Al-Dandal · Senior Financial Analyst — Investment Plan

    Took 2 days

  3. Project manager certifies⁦2026-02-23⁩

    Eng. Qasem Al-Hariri · Director, Transport & Housing Projects

    Took 3 days

  4. Payment order prepared⁦2026-02-26⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-01⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneSupervision to provisional acceptanceIn progress · ⁦2027-03-11⁩
  2. Project milestoneMS-G5Final handoverMilestone not approved yet

Deliverables & completion certificates

No deliverable is tied to this milestone — the evidence is the milestone’s approval and its files.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderHuda Al-Dandal → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Qasem Al-Hariri → Rasha Al-Mudarres

Certificate history

1 March 2026

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2026-03-01 13:00

26 February 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-02-26 13:00

23 February 2026

  1. Approval: Eng. Qasem Al-Hariri signed “Project manager certifies”

    2026-02-23 13:00

20 February 2026

  1. Approval: Huda Al-Dandal signed “Engineer verifies quantities”

    2026-02-20 13:00

18 February 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-02-18 09:00