PSA/2024/014
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
45% of the current value paid
Paid
SYP302.5Mof a current value of SYP 670M
Value of each certificate
The last 14 — gross and net
Approved: 20
Count: 20 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | Net | Status | |
|---|---|---|---|---|---|---|---|
| Certificate 20September 2026 | 2026-10-06 | SYP6.5M | SYP325K | SYP0 | SYP6.2M | Approved | |
| Certificate 19August 2026 | 2026-08-21 | SYP8.8M | SYP437.5K | SYP0 | SYP8.3M | Approved | |
| Certificate 18June 2026 | 2026-07-06 | SYP12M | SYP600K | SYP0 | SYP11.4M | Approved | |
| Certificate 17May 2026 | 2026-05-21 | SYP12.5M | SYP625K | SYP0 | SYP11.9M | Approved | |
| Certificate 16March 2026 | 2026-04-05 | SYP15.5M | SYP775K | SYP0 | SYP14.7M | Approved | |
| Certificate 15January 2026 | 2026-02-18 | SYP18.3M | SYP912.5K | SYP0 | SYP17.3M | Approved | |
| Certificate 14December 2025 | 2026-01-03 | SYP16.5M | SYP825K | SYP0 | SYP15.7M | Approved | |
| Certificate 13October 2025 | 2025-11-18 | SYP20.8M | SYP1M | SYP0 | SYP19.7M | Approved | |
| Certificate 12September 2025 | 2025-10-03 | SYP20.8M | SYP1M | SYP0 | SYP19.7M | Approved | |
| Certificate 11July 2025 | 2025-08-18 | SYP18.8M | SYP937.5K | SYP0 | SYP17.8M | Approved | |
| Certificate 10June 2025 | 2025-07-04 | SYP22.8M | SYP1.1M | SYP0 | SYP21.6M | Approved | |
| Certificate 9April 2025 | 2025-05-19 | SYP19.3M | SYP962.5K | SYP0 | SYP18.3M | Approved | |
| Certificate 8March 2025 | 2025-04-03 | SYP18.8M | SYP937.5K | SYP0 | SYP17.8M | Approved | |
| Certificate 7January 2025 | 2025-02-16 | SYP20.3M | SYP1M | SYP0 | SYP19.2M | Approved | |
| Certificate 6December 2024 | 2025-01-01 | SYP15.5M | SYP775K | SYP0 | SYP14.7M | Approved | |
| Certificate 5October 2024 | 2024-11-16 | SYP15.8M | SYP787.5K | SYP0 | SYP15M | Approved | |
| Certificate 4September 2024 | 2024-10-01 | SYP14M | SYP700K | SYP0 | SYP13.3M | Approved | |
| Certificate 3July 2024 | 2024-08-16 | SYP10.3M | SYP512.5K | SYP0 | SYP9.7M | Approved | |
| Certificate 2June 2024 | 2024-07-01 | SYP9.3M | SYP462.5K | SYP0 | SYP8.8M | Approved | |
| Certificate 1April 2024 | 2024-05-16 | SYP6.5M | SYP325K | SYP0 | SYP6.2M | Approved |