Syrian Arab Republic
Planning and Statistics Authority
General Directorate of Finance & Contracts — Contracts & Procurement Directorate
- Certificate no.
- 14
- Date
- 2025-08-31
- Reference
- PAY-2024-006-14
Interim payment certificate no. (14)
For the work of August 2025
- Contract number
- PSA/2024/006
- Tender file no.
- 2401430082
- Contract
- Hama National Hospital extension — civil & MEP works
- Contractor
- Al-Fayhaa General Contracting Co.
- Contractor tax number
- TX-412548
- Project
- Hama National Hospital Upgrade & Extension
- Contract period
- 2024-03-03 — 2026-12-31
- Original contract value
- SYP14,000,000,000
- Current contract value
- SYP14,600,000,000including variations of SYP 600M
- Linked milestone
- Structure complete · MS-G3 Build complete
Certificate summary (SYP)
| 1 | Total value of work completed to date | 5,798,750,000 |
| 2 | Less: previous certificates | (5,335,000,000) |
| 3 | Value of work in this certificate | 463,750,000 |
| 4 | Less: retention (10%) | (46,375,000) |
| 5 | Less: advance payment recovery (10%) | (46,375,000) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (92,750,000) |
| 8 | Net amount payable to the contractor | SYP371,000,000 |
Amount in words: Three hundred seventy-one million Syrian pounds only
Retention held up to this certificate: SYP 579.9M — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 1,022,000,000 | 871,375,000 | 65,100,000 | 936,475,000 | 92% |
| Earthworks & foundations | 2,628,000,000 | 1,355,650,000 | 105,625,000 | 1,461,275,000 | 56% |
| Concrete & structural works | 4,526,000,000 | 1,818,150,000 | 159,225,000 | 1,977,375,000 | 44% |
| Mechanical, electrical & plumbing | 3,504,000,000 | 885,025,000 | 89,175,000 | 974,200,000 | 28% |
| Finishes & external works | 2,190,000,000 | 352,900,000 | 38,525,000 | 391,425,000 | 18% |
| Testing & commissioning | 730,000,000 | 51,900,000 | 6,100,000 | 58,000,000 | 8% |
| Total | 14,600,000,000 | 5,335,000,000 | 463,750,000 | 5,798,750,000 | 40% |
Amounts in Syrian pounds.
Signatures and approvals
Contractor’s representative
Eng. Walid Al-Masri
Supervising engineer
Eng. Wael Al-Khawlani
Project manager
Eng. Sara Al-Barazi
Finance & contracts
Omar Al-Nahhas
Final approver
Dr. Samer Al-Daqqar