Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

A ready substitution plan for every critical vendor role

LL-052 · Vendor · High impact · In PMO review

  1. 1ContextTwo vendor integration engineers left at the peak of the civil-registry and interoperability work.
  2. 2What happenedThe contract had no substitution deadline, so both seats sat empty for two weeks.
  3. 3ImpactIntegration progress fell; ⁦the integration milestone slipped 40 days⁩.

Recommendation

A ⁦named-team clause with 10⁩-day substitution and a penalty in contract templates.

Captured by
Eng. Tarek Al-Mardini
Date
2026-10-12
Applies to
Digital · IT