Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

A fallback test environment for national integrations

LL-049 · Integration · Medium impact · In PMO review

  1. 1ContextThe shared civil-registry test environment was down for nine days.
  2. 2What happenedThe integration team stopped entirely — there was no local simulator.
  3. 3Impact⁦About 60 person-days lost⁩.

Recommendation

Build a simulator of the national interfaces in the first integration sprint.

Captured by
Hamza Al-Hussein
Date
2026-10-09
Applies to
Digital