Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Settle the land handover before award, not after

LL-029 · Procurement · High impact · Published

  1. 1ContextThe Darayya replacement housing project.
  2. 2What happened⁦The site was handed over piecemeal because 14 plots had not yet been released by the bodies that held them⁩.
  3. 3ImpactA ⁦120-day extension claim and SYP⁩ ⁦170M compensation⁩.

Recommendation

Make “land available” a mandatory approval-gate item.

Captured by
Eng. Qasem Al-Hariri
Date
2025-06-10
Applies to
Infrastructure · Construction