Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Lessons learned

Lessons by category, surfaced when a similar project is created.

Published lessons
19

From ⁦17⁩ projects

Times cited
85

In later requests and projects

High impact
10

Cost days or money

In review
2

Waiting for PMO validation

Where lessons recur

Lessons per category · times cited

Press a category to filter the register.

Suggested for a similar project

Pick a project; lessons rank by type, phase, portfolio and proven reuse.

A Infrastructure project in Planning

  1. 99Same project typeFits its phaseSame portfolioProven
  2. 80Same project typeFits its phaseProven
  3. 80Same project typeFits its phaseProven
  4. 78Same project typeFits its phaseProven
  5. 70Same project typeFits its phase

The register

Each lesson: context, what happened, impact, recommendation.

⁦21⁩ of ⁦21⁩

Tie payments to accepted deliverables, not elapsed time

LL-021 · Finance & funding · Medium impact · Published

  1. 1ContextThe digital signature & document e-verification build contract.
  2. 2What happenedA ⁦20% payment was released before the stage passed acceptance⁩.
  3. 3Impact⁦Hard to hold the vendor to 37 open defects⁩.

Recommendation

A payment schedule tied to deliverable acceptance in every digital contract.

Captured by
Omar Al-Nahhas
Date
2025-08-30
Applies to
Digital · IT · Service

Where it was used (⁦3⁩)