Certificate ⁦7⁩ — September 2026

As-Suwayda trunk lines & water network — rehabilitation works

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
7
Date
⁦2026-10-06⁩
Reference
PAY-2025-024-07

Interim payment certificate no. (⁦7⁩)

For the work of September 2026

Contract number
PSA/2025/024
Tender file no.
2504790706
Contract
As-Suwayda trunk lines & water network — rehabilitation works
Contractor
Hauran Construction Co.
Contractor tax number
TX-443918
Project
Suwayda Drinking-Water Network from Al-Ain Dam
Contract period
⁦2025-11-02⁩ — ⁦2027-09-30⁩
Original contract value
SYP825,000,000
Current contract value
SYP825,000,000
Linked milestone
Structure complete · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date287,500,000
2Less: previous certificates(262,750,000)
3Value of work in this certificate24,750,000
4Less: retention (⁦10%⁩)(2,475,000)
5Less: advance payment recovery (⁦10%⁩)(2,475,000)
6Less: delay and breach penalties0
7Total deductions(4,950,000)
8Net amount payable to the contractorSYP19,800,000

Amount in words: Nineteen million eight hundred thousand Syrian pounds only

Retention held up to this certificate: SYP 28.8M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation57,750,00042,875,0003,550,00046,425,000⁦80%⁩
Earthworks & foundations148,500,00066,725,0005,725,00072,450,000⁦49%⁩
Concrete & structural works255,750,00089,550,0008,500,00098,050,000⁦38%⁩
Mechanical, electrical & plumbing198,000,00043,650,0004,650,00048,300,000⁦24%⁩
Finishes & external works123,750,00017,400,0002,000,00019,400,000⁦16%⁩
Testing & commissioning41,250,0002,550,000325,0002,875,000⁦7%⁩
Total825,000,000262,750,00024,750,000287,500,000⁦35%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Bilal Al-Masalmeh

Al-Masalmeh⁦2026-10-06⁩

Supervising engineer

Eng. Wael Al-Khawlani

Al-Khawlani⁦2026-10-08⁩

Project manager

Eng. Rami Youssef

Youssef⁦2026-10-11⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-10-14⁩

Final approver

Rasha Al-Mudarres

Al-Mudarres⁦2026-10-17⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-10-06⁩

    Eng. Bilal Al-Masalmeh

  2. Engineer verifies quantities⁦2026-10-08⁩

    Eng. Wael Al-Khawlani · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-10-11⁩

    Eng. Rami Youssef · Director, Renewable Energy & Environment Projects

    Took 3 days

  4. Payment order prepared⁦2026-10-14⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-10-17⁩

    Rasha Al-Mudarres · Director General, Finance & Contracts

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneStructure completeIn progress · ⁦2026-11-20⁩
  2. Project milestoneMS-G3Build completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Rasha Al-Mudarres
  • Whoever verified quantities does not prepare the payment orderEng. Wael Al-Khawlani → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Rami Youssef → Rasha Al-Mudarres

Certificate history

17 October 2026

  1. Payment: Rasha Al-Mudarres signed “Final approval”

    2026-10-17 13:00

14 October 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-10-14 13:00

11 October 2026

  1. Approval: Eng. Rami Youssef signed “Project manager certifies”

    2026-10-11 13:00

8 October 2026

  1. Approval: Eng. Wael Al-Khawlani signed “Engineer verifies quantities”

    2026-10-08 13:00

6 October 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-10-06 09:00