Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية

Certificate ⁦5⁩ — February 2026

Cybersecurity programme & SOC delivery

Syrian Arab Republic

Planning and Statistics Authority

General Directorate of Finance & Contracts — Contracts & Procurement Directorate

Certificate no.
5
Date
⁦2026-03-18⁩
Reference
PAY-2025-004-05

Interim payment certificate no. (⁦5⁩)

For the work of February 2026

Contract number
PSA/2025/004
Tender file no.
2503390446
Contract
Cybersecurity programme & SOC delivery
Contractor
Al-Hisn Cybersecurity Co.
Contractor tax number
TX-431370
Project
Government Network Cybersecurity Programme
Contract period
⁦2025-03-02⁩ — ⁦2026-12-15⁩
Original contract value
SYP787,500,000
Current contract value
SYP787,500,000
Linked milestone
Integration & UAT · MS-G3 Build complete

Certificate summary (SYP)

1Total value of work completed to date482,500,000
2Less: previous certificates(369,000,000)
3Value of work in this certificate113,500,000
4Less: retention (⁦5%⁩)(5,675,000)
5Less: advance payment recovery (⁦10%⁩)(11,350,000)
6Less: delay and breach penalties0
7Total deductions(17,025,000)
8Net amount payable to the contractorSYP96,475,000

Amount in words: Ninety-six million four hundred seventy-five thousand Syrian pounds only

Retention held up to this certificate: SYP 24.1M — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Analysis & design118,125,00087,600,00018,550,000106,150,000⁦90%⁩
Licences & platform157,500,00099,575,00025,875,000125,450,000⁦80%⁩
Build & configuration236,250,000108,050,00036,700,000144,750,000⁦61%⁩
Systems integration118,125,00041,400,00016,500,00057,900,000⁦49%⁩
Testing & acceptance78,750,00019,800,0009,150,00028,950,000⁦37%⁩
Training & run78,750,00012,575,0006,725,00019,300,000⁦25%⁩
Total787,500,000369,000,000113,500,000482,500,000⁦61%⁩

Amounts in Syrian pounds.

Signatures and approvals

Contractor’s representative

Eng. Haitham Al-Haj

Al-Haj⁦2026-03-18⁩

Supervising engineer

Hamza Al-Hussein

Al-Hussein⁦2026-03-20⁩

Project manager

Eng. Hussam Zeidan

Zeidan⁦2026-03-23⁩

Finance & contracts

Omar Al-Nahhas

Al-Nahhas⁦2026-03-26⁩

Final approver

Dr. Samer Al-Daqqar

Al-Daqqar⁦2026-03-29⁩
Issued electronically through Munjaz Integration-ready for the ERP contracts & procurement module

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-03-18⁩

    Eng. Haitham Al-Haj

  2. Engineer verifies quantities⁦2026-03-20⁩

    Hamza Al-Hussein · Senior Software Engineer – Integration

    Took 2 days

  3. Project manager certifies⁦2026-03-23⁩

    Eng. Hussam Zeidan · Director, Cybersecurity

    Took 3 days

  4. Payment order prepared⁦2026-03-26⁩

    Omar Al-Nahhas · Senior Finance & Contracts SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-03-29⁩

    Dr. Samer Al-Daqqar · President, Planning and Statistics Authority

    Took 3 days

You are viewing as Dr. Reem Al-Qabbani

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneIntegration & UATDone · ⁦2026-06-02⁩
  2. Project milestoneMS-G3Build completeMilestone approved ⁦2026-06-18⁩1 evidence file

Deliverables & completion certificates

Every linked deliverable is accepted with a completion certificate.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itOmar Al-Nahhas → Dr. Samer Al-Daqqar
  • Whoever verified quantities does not prepare the payment orderHamza Al-Hussein → Omar Al-Nahhas
  • The project manager does not approve the paymentEng. Hussam Zeidan → Dr. Samer Al-Daqqar

Certificate history

29 March 2026

  1. Payment: Dr. Samer Al-Daqqar signed “Final approval”

    2026-03-29 13:00

26 March 2026

  1. Approval: Omar Al-Nahhas signed “Payment order prepared”

    2026-03-26 13:00

23 March 2026

  1. Approval: Eng. Hussam Zeidan signed “Project manager certifies”

    2026-03-23 13:00

20 March 2026

  1. Approval: Hamza Al-Hussein signed “Engineer verifies quantities”

    2026-03-20 13:00

18 March 2026

  1. Approval: Contractor signed “Certificate submitted”

    2026-03-18 09:00
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close