Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
Variations pending: 1 worth SYP 562.5M — if approved the value becomes SYP 6.5B
41% of the current value paid
Paid
of a current value of SYP 5.9B
Open claims
1
of 1 claim
Extension days claimed
None
Amounts claimed
SYP 72.5M
1.2% of the contract value
Extension granted
From earlier claims
Extensions of time, cost claims and disputes
CLM-0010Cost claimIn review
Unforeseen ground conditions on the industrial-city site
Geotechnical survey differs from the tender data