PRJ-2026-035On track1Pre-startAgilePlannedDelivered by:Planning and Statistics Authority

National Development & Reconstruction Forum 2027

Add to watchlist

A national forum at the Damascus Fairground presenting the medium-term plan’s projects and partnership opportunities to investors and partners, and launching the first national development report.

Project managerAyman SabbaghProject sponsorEng. Mustafa Al-Awa

Budget (BAC)

SYP 600M

Actual cost

SYP 0

⁦0%⁩ of budget

Progress

⁦0%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 600M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

Pre-startStage ⁦1⁩ of ⁦5⁩

Next gate:Initiation3 December 2026

  1. Pre-start · Current stagePre-start · Current stage
  2. Gate into «Initiation»DecisionNot held yetDate3 December 2026Initiation · Not startedInitiation · Not started
  3. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

0Achieved
0On track
5At risk
0Late
Average delay74 days
Apr 27Jul 27Oct 27Jan 28Apr 28
Contractual
Build completePlanned: ⁦2027-09-07⁩Forecast / actual: ⁦2027-11-24⁩Delay: 78 daysG3 +78
Executive
Project plan approvedPlanned: ⁦2027-04-17⁩Forecast / actual: ⁦2027-05-13⁩Delay: 26 daysG1 +26
Payment
Final handoverPlanned: ⁦2027-12-31⁩Forecast / actual: ⁦2028-04-28⁩Delay: 119 daysG5 +119
Regulatory
Testing & acceptance completePlanned: ⁦2027-11-04⁩Forecast / actual: ⁦2028-02-10⁩Delay: 98 daysG4 +98
Project
Designs approvedPlanned: ⁦2027-06-13⁩Forecast / actual: ⁦2027-07-30⁩Delay: 47 daysG2 +47

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2027-04-17⁩⁦2027-05-13⁩⁦+26⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
Designs approvedMS-G2Project⁦2027-06-13⁩⁦2027-07-30⁩⁦+47⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
Build completeMS-G3Contractual⁦2027-09-07⁩⁦2027-11-24⁩⁦+78⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2027-11-04⁩⁦2028-02-10⁩⁦+98⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
Final handoverMS-G5Payment⁦2027-12-31⁩⁦2028-04-28⁩⁦+119⁩ daysAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦0%⁩

Awaiting acceptance

⁦0%⁩

Not handed in

⁦100%⁩

Deliverable flow

Pick a stage to filter the register
⁦11⁩ results
Export CSV
Project plan & baseline035-D1⁦4%⁩—DraftAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syEng. Mustafa Al-Awa⁦2027-03-19⁩V0⁦0⁩ of ⁦3⁩
Monitoring & reporting035-D2⁦4%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-04-17⁩V0⁦0⁩ of ⁦3⁩
Business requirements035-D3⁦9%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-05-15⁩V0⁦0⁩ of ⁦3⁩
Solution design035-D4⁦9%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-06-13⁩V0⁦0⁩ of ⁦3⁩
Release 1035-D5⁦13%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-07-12⁩V0⁦0⁩ of ⁦3⁩
Release 2035-D6⁦13%⁩—DraftAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syEng. Mustafa Al-Awa⁦2027-08-09⁩V0⁦0⁩ of ⁦3⁩
Integrations035-D7⁦13%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-09-07⁩V0⁦0⁩ of ⁦3⁩
System testing035-D8⁦10%⁩—DraftAyman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.syEng. Mustafa Al-Awa⁦2027-10-06⁩V0⁦0⁩ of ⁦3⁩
User acceptance testing035-D9⁦10%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-11-04⁩V0⁦0⁩ of ⁦3⁩
Training & change035-D10⁦8%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-12-02⁩V0⁦0⁩ of ⁦3⁩
Go-live & handover035-D11⁦7%⁩—DraftEng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.syEng. Mustafa Al-Awa⁦2027-12-31⁩V0⁦0⁩ of ⁦3⁩
Total · 11⁦100%⁩
⁦1⁩–⁦11⁩ of ⁦11⁩