National Development & Reconstruction Forum 2027
Add to watchlistA national forum at the Damascus Fairground presenting the medium-term plan’s projects and partnership opportunities to investors and partners, and launching the first national development report.
Budget (BAC)
Actual cost
0% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
Pre-startStage 1 of 5
Next gate:Initiation3 December 2026
- Pre-start · Current stagePre-start · Current stage
- Gate into «Initiation»DecisionNot held yetDate3 December 2026Initiation · Not startedInitiation · Not started
- Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
- Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2027-04-17 | 2027-05-13 | +26 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-06-13 | 2027-07-30 | +47 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-09-07 | 2027-11-24 | +78 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-11-04 | 2028-02-10 | +98 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-31 | 2028-04-28 | +119 days | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
0%Awaiting acceptance
0%Not handed in
100%Deliverable flow
Display options
| Project plan & baseline035-D1 | 4% | — | Draft | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-03-19 | V0 | 0 of 3 |
| Monitoring & reporting035-D2 | 4% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-04-17 | V0 | 0 of 3 |
| Business requirements035-D3 | 9% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-05-15 | V0 | 0 of 3 |
| Solution design035-D4 | 9% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-06-13 | V0 | 0 of 3 |
| Release 1035-D5 | 13% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-07-12 | V0 | 0 of 3 |
| Release 2035-D6 | 13% | — | Draft | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-08-09 | V0 | 0 of 3 |
| Integrations035-D7 | 13% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-09-07 | V0 | 0 of 3 |
| System testing035-D8 | 10% | — | Draft | Ayman SabbaghAyman SabbaghCensus & National Development Forum ConsultantP-045ayman.sabbagh@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-10-06 | V0 | 0 of 3 |
| User acceptance testing035-D9 | 10% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-11-04 | V0 | 0 of 3 |
| Training & change035-D10 | 8% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-12-02 | V0 | 0 of 3 |
| Go-live & handover035-D11 | 7% | — | Draft | Eng. Mustafa Al-AwaEng. Mustafa Al-AwaDeputy President, PlanningP-047mustafa.alawa@psa.gov.sy | Eng. Mustafa Al-Awa | 2027-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |