Planning and Statistics AuthorityMunjaz11My actionsNotificationsالعربية
PRJ-2026-035On track1Pre-startAgilePlannedDelivered by:Planning and Statistics Authority

National Development & Reconstruction Forum 2027

Add to watchlist

A national forum at the Damascus Fairground presenting the medium-term plan’s projects and partnership opportunities to investors and partners, and launching the first national development report.

Project managerAyman SabbaghProject sponsorEng. Mustafa Al-Awa

Budget (BAC)

SYP 600M

Actual cost

SYP 0

⁦0%⁩ of budget

Progress

⁦0%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SYP 600M

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

Pre-startStage ⁦1⁩ of ⁦5⁩

Next gate:Initiation3 December 2026

  1. Pre-start · Current stagePre-start · Current stage
  2. Gate into «Initiation»DecisionNot held yetDate3 December 2026Initiation · Not startedInitiation · Not started
  3. Gate into «Planning»DecisionNot held yetPlanning · Not startedPlanning · Not started
  4. Gate into «Execution»DecisionNot held yetExecution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project weight

The weight and the relative weight in the portfolio

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Approval

Project weight

The weight and the relative weight in the portfolio

Form no.
PSA-PMO-F03
Template edition
1.0
Version
V2
Form date
⁦2026-09-16⁩
In approvalPRJ-2026-035National Development & Reconstruction Forum 2027

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-035
Project
National Development & Reconstruction Forum 2027
Portfolio
Digital Government Services & Data Portfolio
Sector
Economic & Social Planning Sector
Sponsor
Eng. Mustafa Al-Awa
Project manager
Ayman Sabbagh

1Weight and relative weightAuto-filled

Project weight score

59 of 100

Relative weight in the portfolio

⁦12.7%⁩

Counts once the project is approved

Portfolio

Digital Government Services & Data Portfolio

7 projects

Its share of the portfolio’s progress

0.0 points of 61.1%

2Weight criteriaAuto-filled

Each criterion is rated 1–5 from the project’s record and multiplied by its approved weight.

CriterionRated fromWeightRatingPoints
Strategic importanceThe project’s strategic value⁦35%⁩321.0
Budget sizeApproved budget (BAC)⁦25%⁩210.0
Impact on citizens & beneficiariesThe project’s alignment score⁦20%⁩416.0
Complexity & riskThe project’s risk score⁦10%⁩24.0
Project classificationThe project’s classification⁦10%⁩48.0
Weight score—⁦100%⁩—59

3Relative weights across the portfolioAuto-filled

Proposed and cancelled projects are left out; suspended ones keep their frozen progress.

ProjectScoreRelative weightProgress
Unified Government e-Services Platform88⁦21.8%⁩⁦58%⁩
National Statistical Indicators & Open Data Portal70⁦17.3%⁩⁦62%⁩
Medium-Term Plan Implementation Tracker (ministries & governorates)66⁦16.3%⁩⁦1%⁩
e-Litigation & Judicial Notification Platform — Release 263⁦15.6%⁩⁦91%⁩
Government Services Mobile App — New Release63⁦15.6%⁩⁦64%⁩
Digital Signature & e-Verification of Government Documents — Phase 154⁦13.4%⁩⁦100%⁩
National Development & Reconstruction Forum 202759Not counted⁦0%⁩
Weighted portfolio progress—⁦100%⁩⁦61.1%⁩

Approval logChain: Project weight approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Mariam Al-ZoubiDirector, Education & Rural Development ProjectsSubmitted—⁦2026-09-16⁩ 10:25
2Weight model complianceMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-09-20⁩ 12:39

Signatures

Weight model compliance

Mariam Al-Zoubi

Approved⁦2026-09-20⁩

Portfolio manager approval

Basel Al-Mahayni

Awaiting decision

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F03 · version V2

Project weight

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project weight approval · version ⁦1⁩

Submitted by Mariam Al-Zoubi on ⁦2026-09-16⁩

  1. Methodology review

    Weight model compliance

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-09-20⁩ at ⁦12:39⁩

  2. Technical acceptance

    Portfolio manager approval

    Basel Al-Mahayni · Portfolio manager
    1 working day leftWithin the time limit · Limit 3 working daysLimit 3 working days · Due ⁦2026-10-29⁩
    Waiting on Basel Al-Mahayni

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-09-14⁩

    Classification added at 10; budget cut from 35 to 25 so the building projects do not swamp the portfolio

    Dr. Reem Al-Qabbani

  2. V1Approved⁦2025-12-02⁩

    First model: strategic importance, budget, impact, complexity

    Dr. Reem Al-Qabbani

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close