Planned to date 4%
- SPI
- 1.00
- Forecast finish
- 2027-12-31
- Budget
- SYP 187.5M
Kick-off of the e-learning platform and computer labs for Raqqa schools: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.
Held on
30 August 202610:00 – 11:20
Kick-off minutes
Roles, tasks, decisions and the start of execution — the «kick-off minutes» form.
Approves the plan and rules on what exceeds the PM’s authority
Sets the teachers’ training needs on the platform
Runs the plan and the team and files the periodic update card
Signs off the digital curriculum content with the Ministry of Education and accepts the deliverables
Gathers requirements and writes the use cases
Communication and user-training plan
Gather the fifty schools’ needs with the Raqqa education directorate
Yasmine Bitar · 2026-09-24 · Done
Draft the tender book for the learning platform and computer labs
Mariam Al-Zoubi · 2026-10-15 · Done
Communication plan with the education directorate and school heads
Ola Al-Jandali · 2026-10-08 · Done
Approve the project management plan and baseline at the planning gate
Mariam Al-Zoubi · 2026-11-19 · Open
Planned start 2026-08-31
Eng. Abdulrahman Al-Kilani confirmed execution started on 2026-08-30
70 of 90 min
The approved charter: objective, scope, deliverables, budget
For informationMariam Al-Zoubi
20 min
Roles, responsibilities and communication
ApprovalMariam Al-Zoubi
20 min
First tasks and the six-week plan
DecisionYasmine Bitar
20 min
Start-of-execution confirmation
ApprovalEng. Abdulrahman Al-Kilani
10 min
Approved and locked
1. The approved charter: objective, scope, deliverables, budget
PRJ-2026-029The charter was presented as approved at the initiation gate, unchanged.
2. Roles, responsibilities and communication
The roles matrix was agreed; a weekly team meeting every Sunday and a periodic update card every two weeks.
3. First tasks and the six-week plan
Four first tasks assigned with owners and dates.
4. Start-of-execution confirmation
The sponsor confirmed execution starts on 2026-08-31.
No decisions recorded
They show in the task register and on the owner’s calendar
No tasks from this meeting yet
Project meeting — no quorum required
2 files
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
Planned to date 4%
Agenda item needing a decision
First tasks and the six-week plan
From item 3
Nothing
Nothing