UAT results — Ministry of Finance e-archiving
Ministry of Finance e-Archiving
1. Executive summary
This report gives the position of Ministry of Finance e-Archiving to date: 95% complete against 100% planned, SPI 0.95, CPI 1.00, and an estimate at completion of SYP 355M.
- Project
- Ministry of Finance e-Archiving (PRJ-2026-017)
- Project manager
- Nour Al-Jabiri
- Budget
- SYP 355M
- Progress
- 95% actual against 100% planned
- Forecast finish
- 2026-11-15
2. Key findings
- All planned milestones of the period met except one deferred
- Actual spend rose in line with the work done
- Three high risks under treatment, each with a named owner
3. Recommendations & decisions needed
- Approve the proposed treatment of the high risks
- Track the open findings with the vendor weekly
Prepared by
Nour Al-Jabiri