DMD-2026-001

Rehabilitation of 40 schools in eastern Aleppo

EvaluationIdea
Electronic formPriority evaluation
Priority score
74

Score confirmed by the evaluation panel

Estimated cost
SYP 237.5M
Net present value
SYP 179.9M
Internal rate of return
⁦28.6%⁩
Payback period
⁦3.0⁩ years
Rank in the 2027 plan
#3

of ⁦9⁩ candidates

  1. Gate into «Submitted»DecisionGoDate11 February 2026DraftComplete
  2. Gate into «Initial review»DecisionGoDate1 May 2026SubmittedComplete
  3. Gate into «Feasibility»DecisionGoDate18 July 2026Initial reviewComplete
  4. Gate into «Evaluation»DecisionGoDate5 October 2026FeasibilityComplete
  5. Gate into «Committee review»DecisionNot held yetEvaluationCurrent stageCurrent stage
  6. Gate into «Approved»DecisionNot held yet6Committee reviewNot started
  7. Gate into «Prioritized»DecisionNot held yet7ApprovedNot started
  8. Gate into «Converted to project»DecisionNot held yet8PrioritizedNot started
  9. 9Converted to projectNot started
P2P2 · High priority — score ⁦74⁩ of 100

Priority class

High priority

Computed from the score and the approved model’s thresholds; may be changed with a reason kept in the history

By the model: P2 (score ⁦74⁩)

Class thresholds

P1⁦75⁩–⁦100⁩P2⁦60⁩–⁦74⁩P3⁦45⁩–⁦59⁩P4⁦0⁩–⁦44⁩

The approved model (version ⁦4⁩) with the eleven criteria; the score is the weighted mean of the ratings scaled to 100.

Evaluation against the priority model

CriterionWeightRating (1–5)Contribution
Value
Fit with the development frameworkHow far the proposal moves the objectives of the 2026–2030 development framework, its six pillars and the initiatives and KPIs of the 2026–2028 medium-term plan.Raises priority20%4.517.5
Development valueThe value it adds for citizens and the governorates: a public service restored, infrastructure rehabilitated or a new national capability.Raises priority12%4.510.5
Economic & social returnThe economic and social return in the feasibility study, and its contribution to rationalised investment spending and restored production.Raises priority8%3.85.6
Urgency & compliance
UrgencyThe cost of delay: what citizens and the beneficiary bodies lose if work does not start this year.Raises priority10%3.56.3
Legal requirementIs it required by a law, a decree, a Council of Ministers decision or a directive from a control body or the competent ministry (Ministry of Communications and IT, the Central Organisation for Financial Control)?Raises priority10%1.41.0
Impact
Impact on citizens & beneficiariesIts direct effect on citizens, returning families, students, patients and farmers: time, effort, cost and satisfaction.Raises priority14%4.713.0
Sustainability impactIts contribution to energy and water efficiency in public facilities, renewable energy and lower emissions.Raises priority3%3.72.0
Digital transformation impactIts contribution to digital government services, public-body processes and the use of statistical data.Raises priority5%4.74.6
Effort & risk
RiskDelivery, technical and contractual risk — the higher it is, the lower the priority.Lowers priority7%1.95.4
ComplexityThe number of bodies, governorates, systems, integrations and procedure changes involved.Lowers priority6%2.53.8
Resource requirementThe team, budget and scarce skills it draws from the portfolio’s capacity.Lowers priority5%1.84.0
Priority scoreScore confirmed by the evaluation panel74 / 100

Evaluation profile

This request’s ratings against the average approved request

Evaluation profile
  • This request
  • Approved average
Evaluation profile
CategoryThis requestApproved average
Alignment8894
Value8891
Return7077
Urgency6379
Regulatory1027
Risk7889
Complexity6379
Resources8091
Beneficiary9363
Sustainability6830
Digital9358

Evaluation panel

The request goes to committee only when everyone has signed

  • Kinan Azzam

    Senior Digital Delivery Consultant — National PMO

    Direct effect on 24,000 pupils and low risk

    Signed 2026-10-12
  • Huda Al-Dandal

    Senior Financial Analyst — Investment Plan

    Convincing social return; costs well estimated

    Signed 2026-10-15
  • Eng. Rita Ghanem

    Enterprise Architect

    Fits the school building code

    Signed 2026-10-16