RSK-0040Hasakah Wheat Digital Crop Survey
Field enumerators covering too little of the wheat area
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Wide sown areas and remote villages, and some farmers wary of sharing their holding data
Preventive controls
- Introductory sessions with farmers at the extension units, led by the Hasakah agriculture directorate
- Pilot the short questionnaire with one hundred holdings
2 / 2
Event
Field enumerators covering too little of the wheat area
Under 40% of the target villages covered in two rounds in a row
Contingency
Fill the estimate with satellite imagery for the villages not covered
Impact
Gaps in the wheat-area estimate, and a less accurate reception and payment plan
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 6.3M
Residual
56% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 34 days ago · Outside the engine — below «high»
Project manager
Current levelMariam Al-Zoubi
Currently followed up here- 2
Programme manager
Mariam Al-Zoubi
- 3
PMO director
Dr. Reem Al-Qabbani
- 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Introductory sessions with farmers at the extension units, led by the Hasakah agriculture directorate
Eng. Abdulrahman Al-KilaniEng. Abdulrahman Al-KilaniDeputy President, Development Projects Follow-upP-010abdulrahman.alkilani@psa.gov.syIn progressIn 18 days2026-11-15Pilot the short questionnaire with one hundred holdings
Ola Al-JandaliOla Al-JandaliChange Management SpecialistP-035ola.aljandali@psa.gov.syNot startedIn 53 days2026-12-20
Trigger
Under 40% of the target villages covered in two rounds in a row
Contingency
Fill the estimate with satellite imagery for the villages not covered