RSK-0019Government Backup Data Centre, Homs — Phase 2
Exchange-rate swings on imported equipment with unfixed prices
A risk's detail, response, contingency and residual risk.
Risk statement
From cause to event to impact — with the preventive controls before the event and the contingency after it
Cause
Price swings and unplanned financial commitments
Preventive controls
- Monthly EAC monitoring
- Fix prices in the coming purchase orders
2 / 2
Event
Exchange-rate swings on imported equipment with unfixed prices
EAC above budget by more than 5%
Contingency
Reallocate from the portfolio reserve
Impact
Budget overrun and the need for more funding
Assessment
The level before and after the response
Inherent
Residual
Exposure
SYP 185M
Residual
63% off the score
Score trend
Last six months
- Score
- Target residual
Escalation path
Escalation engine: a high risk unreviewed for 10 days notifies the PM, 15 the programme manager, 20 the PMO director
Last reviewed 7 days ago
Project manager
Current levelEng. George Haddad
Currently followed up here- 2
Programme manager
Eng. George Haddad
Automatically at 15 days unreviewed · in 8 days - 3
PMO director
Dr. Reem Al-Qabbani
Automatically at 20 days unreviewed · in 13 days - 4
Executive Council
Dr. Samer Al-Daqqar
By the PMO director’s decision
Mitigation plan
Each action with its owner and date — tick it off when complete
Monthly EAC monitoring
Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.syIn progressIn 23 days2026-11-20Fix prices in the coming purchase orders
Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.syNot startedIn 23 days2026-11-20
Trigger
EAC above budget by more than 5%
Contingency
Reallocate from the portfolio reserve