PRJ-2026-033 · From item 2
Al-Mayadin General HospitalPlanned to date 2%
- SPI
- 1.00
- Forecast finish
- 2028-12-31
- Budget
- SYP 5.3B
184 days lateMaterial risks: 1
Method compliance and data quality.
Held on
22 October 202611:00 – 11:55
45 of 60 min
October data-quality scorecard
For informationNizar Abu Fakhr
25 min
Al-Mayadin hospital — hold
DecisionDr. Reem Al-Qabbani
20 min
Approved and locked
1. October data-quality scorecard
Compliance & data qualityFour projects below 60%; roll out the standard periodic update card.
2. Al-Mayadin hospital — hold
PRJ-2026-033On hold until the land is allocated.
Voting rule: Simple majority; the chair holds the casting vote
Al-Mayadin hospital suspended pending land allocation
DEC-2026-041Hold
For 6Against 0Abstain 0Carried
They show in the task register and on the owner’s calendar
ACT-0322Dr. Reem Al-Qabbani
Quorum: Four of eight members, including the chair or vice-chair
At least 4 voting members needed
1 file
Drafted by the assistant from the agenda, the minutes, the decisions and the tasks. Review it before approval.
Shown only to invitees and the PMO, and leaves out what your permissions do not let you see.
Built automatically from the projects on the agenda: a card per project, the decisions needed, the support requested and the overdue tasks.
PRJ-2026-033 · From item 2
Al-Mayadin General HospitalPlanned to date 2%
184 days lateMaterial risks: 1
Agenda item needing a decision · PRJ-2026-033
Al-Mayadin hospital — holdFrom item 2
Nothing
Nothing