Project proposal & feasibility study

An electronic form with an auto-filled header, an approval path and its versions, printed with its approval log.

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
PSA-PMO-F01
Template edition
2.1
Version
V1
Form date
⁦2026-03-04⁩
In approvalDMD-2026-002Homs old souq reconstruction

Auto-filled — Filled by the platform from the project record, not typed.

Proposal no.
DMD-2026-002
Proposal
Homs old souq reconstruction
Portfolio
Reconstruction & Infrastructure Portfolio
Sector
Statistics Sector
Sponsor
Eng. Wassim Al-Azm
Proposed by
Dr. Firas Al-Obaid

1The proposalAuto-filled

TitleAuto-filled
Homs old souq reconstruction
Proposed byAuto-filled
Dr. Firas Al-Obaid
DepartmentAuto-filled
National Accounts & Prices Directorate
Submitted onAuto-filled
⁦2026-03-04⁩
Proposal numberAuto-filled
DMD-2026-002

2Justification

The problem or need

Homs old souq and its covered markets were damaged; hundreds of craft and trade shops closed and their owners moved to the city’s edges.

Today

62% of the shops are closed, the stone roofs of three markets are at risk of collapse, and most of the souq has no working power or drainage.

3Objectives

  1. Rebuild the souq in phases while keeping its heritage character, and reopen 80% of the shops within three years.

Strategic objectives served

  • SO-1.1 — Stimulate growth, restore production and attract investment
  • SO-3.1 — Better access to health and education

4Expected benefits

KindBenefit
RevenueTrade activity of about SYP 110M a month back in the souq
Productivity600 craftspeople back in their workshops
ComplianceA registered heritage site protected under the antiquities rules

5Cost & feasibilityAuto-filled

Estimated cost

SYP 155M

Net present value

SYP 158.2M

Return on investment

⁦95%⁩

Payback

2.6 years

YearCapexOpexBenefit
2027SYP 100MSYP 0SYP 0
2028SYP 55MSYP 15MSYP 45M
2029SYP 0SYP 15MSYP 85M
2030SYP 0SYP 16.3MSYP 102.5M
2031SYP 0SYP 16.3MSYP 110M
2032SYP 0SYP 17.5MSYP 115M

6Initial risks

RiskLevelProposed response
Supplier delay in delivery or implementationMediumDelay penalties and a phased delivery plan
Complex old shop ownership and leasesHighA settlement committee with Homs Governorate before the works

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dr. Firas Al-ObaidDeputy President, StatisticsSubmitted—⁦2026-03-04⁩ 13:46
2Line manager endorsementTechnical acceptanceEng. Lina Al-AttarThe requester’s line managerApproved—⁦2026-03-05⁩ 09:30
3PMO reviewMethodology reviewMariam Al-ZoubiPMO — analystApproved—⁦2026-03-09⁩ 10:37
4Portfolio manager reviewTechnical acceptanceApproval enginePortfolio managerPre-breach alert—⁦2026-09-17⁩ 08:00
5Portfolio manager reviewTechnical acceptanceApproval engineEscalated automatically to PMO — director (Dr. Reem Al-Qabbani) on ⁦2026-09-21⁩Automatic escalation—⁦2026-09-21⁩ 08:05

Signatures

Line manager endorsement

Eng. Lina Al-Attar

Approved⁦2026-03-05⁩

PMO review

Mariam Al-Zoubi

Approved⁦2026-03-09⁩

Portfolio manager review

Eng. Wassim Al-Azm

Awaiting decision

Cost & funding review

Rasha Al-Mudarres

Later

Project Approval Committee

Dr. Reem Al-Qabbani

Later

Issued from Munjaz — Planning and Statistics Authority · ⁦2026-10-28⁩Form PSA-PMO-F01 · version V1

Project proposal & feasibility study

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Dr. Firas Al-Obaid on ⁦2026-03-04⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Lina Al-Attar · The requester’s line manager

    Approved · ⁦2026-03-05⁩ at ⁦09:30⁩

  2. Methodology review

    PMO review

    Mariam Al-Zoubi · PMO — analyst

    Approved · ⁦2026-03-09⁩ at ⁦10:37⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Wassim Al-Azm · Portfolio manager
    29 working days overdueAction time limit exceeded · Limit 3 working daysLimit 3 working days · Due ⁦2026-09-17⁩

    Pre-breach alert at ⁦75%⁩ — sent ⁦2026-09-17⁩

    Escalated automatically to PMO — director (Dr. Reem Al-Qabbani) on ⁦2026-09-21⁩

    Waiting on Eng. Wassim Al-Azm
  4. Financial approval

    Cost & funding review

    Rasha Al-Mudarres · Finance

    On the path because: Financial link?

    Delegated to Omar Al-Nahhas

    Limit 4 working days · Expected by ⁦2026-09-23⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Reem Al-Qabbani · Project Approval Committee

    Limit 5 working days · Expected by ⁦2026-09-30⁩

Previous versions

Every version is kept with its status and what changed.

  1. V1In approvalCurrent⁦2026-03-04⁩

    First version of the proposal

    • Filled from the proposal wizard

    Dr. Firas Al-Obaid

Only one version so far.