“Al-Shahbaa Construction & Rehabilitation Co.” is 95 days late and it affects “Aleppo 230 kV Substations Rehabilitation” and “Latakia University Technical Engineering Faculty Extension” and 1 more
Dependencies between projects, programmes and vendors, and knock-on delay.
across 36 items
beyond their float
half the float used
outside the Authority’s control
through delay propagation
When a party’s delay exceeds the float, it carries on to whatever depends on it — these are the chains that need action now
“Al-Shahbaa Construction & Rehabilitation Co.” is 95 days late and it affects “Aleppo 230 kV Substations Rehabilitation” and “Latakia University Technical Engineering Faculty Extension” and 1 more
“Electricity transmission & distribution establishment” is 75 days late and it affects “Darayya Replacement Housing” and “Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate” and 1 more
“Integrated Digital Solutions Co.” is 43 days late and it affects “Unified Government e-Services Platform” and “Government Services Mobile App — New Release” and 1 more
“Ministry of Interior (civil registry)” is 40 days late and it affects “Unified Government e-Services Platform” and “Government Services Mobile App — New Release” and 1 more
Tasks, projects, programmes, vendors and external entities — hover an item to see what it depends on and what depends on it, click it for its details
Delay simulator
What if an item slips further? Pick it and a number of days to see how far the effect travels.
Extra delay30 days
Each dependency: who waits on whom, for what, by when, with how much float, and the delay it carries now
Display options
DEP-029 Commissioning passed before handover and the substations are energised | Substation bay commissioning (protection & fire)Task | Aleppo 230 kV Substations RehabilitationProject | Finish-to-start | 2026-09-30 | 0 days | 126 days | 126 days | Late | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy |
DEP-031 Stable power for eastern Aleppo after rehabilitation | Aleppo 230 kV Substations RehabilitationProject | Energy & Water Systems Rehabilitation ProgrammeProgramme | Programme outcome | 2027-03-31 | 30 days | 126 days | 96 days | Late | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy |
DEP-027 Transformers and protection bays installed | Al-Shahbaa Construction & Rehabilitation Co.Vendor | Substation bay commissioning (protection & fire)Task | Deliverable | 2026-08-31 | 0 days | 95 days | 95 days | Late | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy |
DEP-018 HV line diversion in block 4 | Electricity transmission & distribution establishmentExternal entity | Darayya Replacement HousingProject | Service | 2026-09-30 | 0 days | 75 days | 75 days | Late | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy |
DEP-021 Replacement housing complete and returning families moved in | Darayya Replacement HousingProject | Damaged Areas Reconstruction ProgrammeProgramme | Programme outcome | 2027-06-30 | 0 days | 75 days | 75 days | Late | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy |
DEP-022 The Douma plant in service with the sewer networks connected | Douma Wastewater Treatment PlantProject | Damaged Areas Reconstruction ProgrammeProgramme | Programme outcome | 2027-05-31 | 0 days | 64 days | 64 days | Late | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy |
DEP-016 Automated financial processes | Integrated Public Financial Management System — Phase 1Project | Integrated Government Systems ProgrammeProgramme | Programme outcome | 2026-12-31 | 0 days | 58 days | 58 days | Late | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy |
DEP-019 Foundations complete before the treatment basins are cast | Treatment-basin foundations, axes 12 to 16Task | Douma Wastewater Treatment PlantProject | Finish-to-start | 2026-12-15 | 0 days | 55 days | 55 days | Late | Eng. Qasem Al-HaririEng. Qasem Al-HaririDirector, Transport & Housing ProjectsP-020qasem.alhariri@psa.gov.sy |
DEP-020 The network, road and lighting standards approved for the Darayya project | Darayya Replacement HousingProject | Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernorateProject | Finish-to-start | 2027-07-31 | 20 days | 75 days | 55 days | Late | Eng. Wael Al-KhawlaniEng. Wael Al-KhawlaniDirector, Engineering Supervision of Construction ProjectsP-036wael.alkhawlani@psa.gov.sy |
DEP-003 Wave 1 government service package | Integrated Digital Solutions Co.Vendor | Wave 1 development (24 government services)Task | Deliverable | 2026-09-30 | 0 days | 43 days | 43 days | Late | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy |
DEP-006 UAT passed before the official launch | User acceptance testingTask | Unified Government e-Services PlatformProject | Finish-to-start | 2027-01-31 | 0 days | 42 days | 42 days | Late | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy |
DEP-011 Programme target: 85% of government services digital | Unified Government e-Services PlatformProject | Government e-Services ProgrammeProgramme | Programme outcome | 2027-03-31 | 0 days | 42 days | 42 days | Late | Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004lina.alattar@psa.gov.sy |
DEP-001 A dedicated civil-registry test environment | Ministry of Interior (civil registry)External entity | Civil-registry & interoperability integration completeTask | Service | 2026-10-31 | 0 days | 40 days | 40 days | Late | Hamza Al-HusseinHamza Al-HusseinSenior Software Engineer – IntegrationP-030hamza.alhussein@psa.gov.sy |
DEP-005 Developed services ready for testing | Wave 1 development (24 government services)Task | User acceptance testingTask | Finish-to-start | 2026-12-01 | 4 days | 43 days | 39 days | Late | Joud HammamiJoud HammamiQA & Testing SpecialistP-033joud.hammami@psa.gov.sy |
DEP-010 Unified platform service APIs for the mobile app | Unified Government e-Services PlatformProject | Government Services Mobile App — New ReleaseProject | Data | 2027-01-15 | 6 days | 42 days | 36 days | Late | Kinan AzzamKinan AzzamSenior Digital Delivery Consultant — National PMOP-041kinan.azzam@psa.gov.sy |
DEP-030 The substation as a practical-training site for the technical engineering students | Aleppo 230 kV Substations RehabilitationProject | Latakia University Technical Engineering Faculty ExtensionProject | Service | 2026-12-31 | 92 days | 126 days | 34 days | Late | Eng. Youssef ShehabiEng. Youssef ShehabiSenior Project Manager — Governorate ProjectsP-023youssef.shehabi@psa.gov.sy |
DEP-004 UAT cannot start before integration is complete | Civil-registry & interoperability integration completeTask | User acceptance testingTask | Finish-to-start | 2026-12-01 | 10 days | 40 days | 30 days | Late | Joud HammamiJoud HammamiQA & Testing SpecialistP-033joud.hammami@psa.gov.sy |
DEP-013 Bank link certified for government fee collection | Bank e-paymentExternal entity | Integrated Public Financial Management System — Phase 1Project | Service | 2026-10-31 | 0 days | 28 days | 28 days | Late | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy |
DEP-015 Cost centres and fee receipts from the financial management system | Integrated Public Financial Management System — Phase 1Project | Civil Registry Automation & Governorate Link-upProject | Data | 2027-03-01 | 30 days | 58 days | 28 days | Late | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy |
DEP-023 Trenching permits for the network in the districts | City councils (trenching permits)External entity | Government Fibre Backbone — Damascus–Homs SegmentProject | Approval | 2026-10-15 | 15 days | 40 days | 25 days | Late | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy |
DEP-007 Backup centre for the ministries’ systems | Government Backup Data Centre, Homs — Phase 2Project | Government Cloud & Ministry Systems MigrationProject | Service | 2026-12-31 | 14 days | 38 days | 24 days | Late | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy |
DEP-002 Updated interoperability-framework interface specification | National interoperability frameworkExternal entity | Civil-registry & interoperability integration completeTask | Deliverable | 2026-10-20 | 25 days | 23 days | — | At risk | Eng. Tarek Al-MardiniEng. Tarek Al-MardiniProject Manager, Unified Government e-Services PlatformP-005tarek.almardini@psa.gov.sy |
DEP-008 Production environment on the government cloud | Government Cloud & Ministry Systems MigrationProject | Unified Government e-Services PlatformProject | Service | 2027-01-31 | 30 days | 24 days | — | At risk | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy |
DEP-009 Conformance review against the government services UX guide | Ministry of Communications and IT (UX guide)External entity | Unified Government e-Services PlatformProject | Approval | 2027-02-15 | 10 days | 0 days | — | On track | Hiba Al-ShamiHiba Al-ShamiSenior Business Analyst — Government ServicesP-006hiba.alshami@psa.gov.sy |
DEP-012 The mobile channel in the programme KPIs | Government Services Mobile App — New ReleaseProject | Government e-Services ProgrammeProgramme | Programme outcome | 2027-01-31 | 40 days | 36 days | — | At risk | Eng. Lina Al-AttarEng. Lina Al-AttarHead of the Unified Government e-Services Platform & Programme Manager, Government e-ServicesP-004lina.alattar@psa.gov.sy |
DEP-014 Financial module customisations | Integrated Financial & Administrative Systems Co.Vendor | Integrated Public Financial Management System — Phase 1Project | Deliverable | 2026-11-15 | 30 days | 21 days | — | At risk | Nour Al-JabiriNour Al-JabiriDirector, Government Systems & IntegrationP-025nour.aljabiri@psa.gov.sy |
DEP-017 Data governance policies (gate condition) | National Statistical Indicators & Open Data PortalProject | Medium-Term Plan Implementation Tracker (ministries & governorates)Project | Approval | 2027-01-31 | 20 days | 18 days | — | At risk | Razan Al-RifaiRazan Al-RifaiDirector, Data & AIP-027razan.alrifai@psa.gov.sy |
DEP-024 The census field offices linked to the secure government network | Government Fibre Backbone — Damascus–Homs SegmentProject | Population & Housing Census Preparation — Phase 1Project | Service | 2027-06-30 | 60 days | 33 days | — | At risk | Eng. Hussam ZeidanEng. Hussam ZeidanDirector, CybersecurityP-026hussam.zeidan@psa.gov.sy |
DEP-025 Network for the unified contact centre | Government Fibre Backbone — Damascus–Homs SegmentProject | Unified Government Contact Centre & AI AssistantProject | Service | 2027-09-30 | 90 days | 33 days | — | On track | Eng. George HaddadEng. George HaddadDirector, Data Centres & Government NetworkP-024george.haddad@psa.gov.sy |
DEP-026 Southern-highway lighting and signal fault reports into the unified contact centre | Damascus–Daraa Highway (Southern M5) — Lighting & Smart SignalsProject | Unified Government Contact Centre & AI AssistantProject | Data | 2027-06-30 | 60 days | 45 days | — | At risk | Eng. Maher Al-HamawiEng. Maher Al-HamawiDirector, Energy, Water & Utilities ProjectsP-021maher.alhamawi@psa.gov.sy |
DEP-028 Syrian Civil Defence safety certificate | Syrian Civil DefenceExternal entity | Substation bay commissioning (protection & fire)Task | Approval | 2026-12-31 | 0 days | 0 days | — | On track | Eng. Rami YoussefEng. Rami YoussefDirector, Renewable Energy & Environment ProjectsP-028rami.youssef@psa.gov.sy |