Project progress, delay & variance report — October 2026

Project progress, delay & variance reportInternal

Planning and Statistics Authority · October 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Project progress, delay & variance report

Project progress, delay & variance report — October 2026

Planning and Statistics Authority

Period
October 2026
Generated
2 October 2026
Submitted to
The President and the Executive Council
Owner
Dr. Reem Al-Qabbani

Prepared by the National PMO — automatically, on Munjaz

Munjaz · RPT-21 · page ⁦1⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Executive summary

Written by Copilot from system data — review before sending

Projects average ⁦51%⁩ progress against ⁦56%⁩ planned, and 14 projects are more than a month behind baseline, by 79 days on average.

The cost forecast at completion exceeds the approved budget by SYP 10.2B; the largest variance is on «Hama National Hospital Upgrade & Extension».

Key figures

Projects
36
Progress
⁦51%⁩ / ⁦56%⁩
Behind baseline
14
Forecast cost variance
SYP 10.2B
Munjaz · RPT-21 · page ⁦2⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Schedule & cost variance

Schedule & cost variance
Schedule & cost variance
CategoryDelay
Al-Mayadin General Hospital184 days
Hama National Hospital Upgrade & Extension152 days
Aleppo 230 kV Substations Rehabilitation126 days
Baniyas Pilot Seawater Desalination Plant123 days
Sheikh Najjar Industrial City Rehabilitation95 days
Darayya Replacement Housing74 days
Douma Wastewater Treatment Plant64 days
Integrated Public Financial Management System — Phase 158 days
Ministry of Finance e-Archiving46 days
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals45 days
Unified Government e-Services Platform42 days
Government Backup Data Centre, Homs — Phase 238 days
Munjaz · RPT-21 · page ⁦3⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Progress vs plan and delay per project

ProjectProgressDelayStatus
Al-Mayadin General HospitalProjects Follow-up⁦2%⁩⁦+184⁩On hold
Hama National Hospital Upgrade & ExtensionProjects Follow-up⁦57%⁩⁦+152⁩Critical
Aleppo 230 kV Substations RehabilitationProjects Follow-up⁦68%⁩⁦+126⁩Critical
Baniyas Pilot Seawater Desalination PlantProjects Follow-up⁦8%⁩⁦+123⁩On hold
Sheikh Najjar Industrial City RehabilitationLocal Development⁦39%⁩⁦+95⁩Off track
Darayya Replacement HousingProjects Follow-up⁦42%⁩⁦+74⁩Off track
Douma Wastewater Treatment PlantProjects Follow-up⁦44%⁩⁦+64⁩Off track
Integrated Public Financial Management System — Phase 1Digital⁦61%⁩⁦+58⁩Off track
Ministry of Finance e-ArchivingDigital⁦95%⁩⁦+46⁩At risk
Damascus–Daraa Highway (Southern M5) — Lighting & Smart SignalsProjects Follow-up⁦79%⁩⁦+45⁩At risk
Unified Government e-Services PlatformDigital⁦58%⁩⁦+42⁩At risk
Government Backup Data Centre, Homs — Phase 2Digital⁦72%⁩⁦+38⁩At risk
Government Fibre Backbone — Damascus–Homs SegmentDigital⁦55%⁩⁦+33⁩At risk

Continued on the next page

Munjaz · RPT-21 · page ⁦4⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Progress vs plan and delay per project

ProjectProgressDelayStatus
Hasakah Wheat Digital Crop SurveyProjects Follow-up⁦63%⁩⁦+31⁩At risk
Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernorateProjects Follow-up⁦33%⁩⁦+28⁩At risk
Government Cloud & Ministry Systems MigrationDigital⁦47%⁩⁦+21⁩At risk
National Statistical Indicators & Open Data PortalStatistics⁦62%⁩⁦+18⁩At risk
Latakia University Technical Engineering Faculty ExtensionProjects Follow-up⁦52%⁩⁦+12⁩At risk
Madinat al-Salam Drinking-Water Network (Quneitra)Projects Follow-up⁦97%⁩⁦+12⁩On track
Civil Registry Automation & Governorate Link-upDigital⁦6%⁩—On track
Deir ez-Zor Suspension Bridge ReconstructionProjects Follow-up⁦2%⁩—On track
Population & Housing Census Preparation — Phase 1Statistics⁦2%⁩—On track
Medium-Term Plan Implementation Tracker (ministries & governorates)Planning⁦1%⁩—On track
Suwayda Drinking-Water Network from Al-Ain DamLocal Development⁦36%⁩—On track
Preparing the 2026–2028 Medium-Term Plan & Governorate PlansStrategy & PMO⁦70%⁩—On track
e-Learning Platform & Computer Labs for Raqqa SchoolsProjects Follow-up⁦4%⁩—On track

Continued on the next page

Munjaz · RPT-21 · page ⁦5⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Progress vs plan and delay per project

ProjectProgressDelayStatus
National Project Risk & Continuity FrameworkStrategy & PMO⁦100%⁩—On track
Government Services Mobile App — New ReleaseLocal Development⁦64%⁩—On track
e-Litigation & Judicial Notification Platform — Release 2Legal⁦91%⁩—On track
Government Network Cybersecurity ProgrammeDigital⁦88%⁩—On track
Ministries Performance Follow-up & National DashboardsStrategy & PMO⁦76%⁩—On track
20 MW Qalamoun Solar FieldProjects Follow-up⁦58%⁩—On track
Munjaz · RPT-21 · page ⁦6⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Schedule & cost variance

ProjectSPICPIBudgetCost variance
Hama National Hospital Upgrade & Extension0.700.82SYP 16BSYP 3.5B
Darayya Replacement Housing0.820.93SYP 29.5BSYP 2.2B
Aleppo 230 kV Substations Rehabilitation0.740.84SYP 10.3BSYP 2B
Sheikh Najjar Industrial City Rehabilitation0.780.89SYP 7.2BSYP 883.7M
Douma Wastewater Treatment Plant0.800.95SYP 8.6BSYP 453.9M
Government Backup Data Centre, Homs — Phase 20.900.91SYP 3.7BSYP 365.9M
Maarat al-Numan Infrastructure Rehabilitation — with Idlib Governorate0.890.96SYP 6BSYP 247.9M
Integrated Public Financial Management System — Phase 10.820.88SYP 1.6BSYP 219.9M
Damascus–Daraa Highway (Southern M5) — Lighting & Smart Signals0.880.94SYP 1.9BSYP 118.1M
Government Fibre Backbone — Damascus–Homs Segment0.870.97SYP 3.3BSYP 102.1M
Unified Government e-Services Platform0.870.96SYP 2.2BSYP 90M
Latakia University Technical Engineering Faculty Extension0.930.98SYP 4BSYP 80.6M
Government Cloud & Ministry Systems Migration0.890.97SYP 1.3BSYP 40.2M
National Statistical Indicators & Open Data Portal0.890.95SYP 537.5MSYP 28.3M
Hasakah Wheat Digital Crop Survey0.880.98SYP 160MSYP 3.3M

Continued on the next page

Munjaz · RPT-21 · page ⁦7⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Schedule & cost variance

ProjectSPICPIBudgetCost variance
Civil Registry Automation & Governorate Link-up1.001.00SYP 600MSYP 0
Ministries Performance Follow-up & National Dashboards1.011.00SYP 245MSYP 0
Ministry of Finance e-Archiving0.951.00SYP 355MSYP 0
Deir ez-Zor Suspension Bridge Reconstruction1.001.00SYP 13BSYP 0
Population & Housing Census Preparation — Phase 11.001.00SYP 1.2BSYP 0
Medium-Term Plan Implementation Tracker (ministries & governorates)1.001.00SYP 700MSYP 0
Unified Government Contact Centre & AI Assistant1.001.00SYP 2.8BSYP 0
Baniyas Pilot Seawater Desalination Plant0.891.00SYP 825MSYP 0
Preparing the 2026–2028 Medium-Term Plan & Governorate Plans1.031.00SYP 80MSYP 0
e-Learning Platform & Computer Labs for Raqqa Schools1.001.00SYP 187.5MSYP 0
Al-Mayadin General Hospital1.001.00SYP 5.3BSYP 0
National Development & Reconstruction Forum 20271.001.00SYP 600MSYP 0
National Project Risk & Continuity Framework1.001.04SYP 90MSYP -3.5M
Digital Signature & e-Verification of Government Documents — Phase 11.001.03SYP 205MSYP -6M
e-Litigation & Judicial Notification Platform — Release 21.011.02SYP 460MSYP -9M

Continued on the next page

Munjaz · RPT-21 · page ⁦8⁩ of ⁦9⁩Internal
Project progress, delay & variance report — October 2026Planning and Statistics Authority

Schedule & cost variance

ProjectSPICPIBudgetCost variance
Government Services Mobile App — New Release1.021.04SYP 315MSYP -12.1M
Government HR System — Employee Self-Service1.001.06SYP 285MSYP -16.1M
Madinat al-Salam Drinking-Water Network (Quneitra)0.981.01SYP 1.7BSYP -16.6M
Suwayda Drinking-Water Network from Al-Ain Dam1.031.02SYP 1.1BSYP -20.6M
20 MW Qalamoun Solar Field1.021.01SYP 2.4BSYP -23.8M
Government Network Cybersecurity Programme1.021.03SYP 965MSYP -28.1M
Munjaz · RPT-21 · page ⁦9⁩ of ⁦9⁩Internal