Deviations & corrective actions report — October 2026 (latest)

Deviations & corrective actions reportInternal

Planning and Statistics Authority · October 2026 (latest)

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

Deviations & corrective actions report

Deviations & corrective actions report — October 2026 (latest)

Planning and Statistics Authority

Period
October 2026 (latest)
Generated
4 October 2026
Submitted to
The President and the Executive Council
Owner
Nizar Abu Fakhr

Prepared by the National PMO — automatically, on Munjaz

Munjaz · RPT-17 · page ⁦1⁩ of ⁦7⁩Internal
Deviations & corrective actions report — October 2026 (latest)Planning and Statistics Authority

Executive summary

Written by Copilot from system data — review before sending

16 KPIs are below the «October 2026 (latest)» target; the largest deviation is «Damaged neighbourhoods covered by reconstruction plans» (⁦−21.9⁩).

The register holds 22 actions; ⁦3⁩ are past their date and ⁦1⁩ closed this month.

Key figures

KPIs below target
16
Open corrective actions
21
Overdue actions
3
Done
1
Munjaz · RPT-17 · page ⁦2⁩ of ⁦7⁩Internal
Deviations & corrective actions report — October 2026 (latest)Planning and Statistics Authority

KPIs off the period target

KPIs off the period target
KPIs off the period target
CategoryDeviation
K-2.2.1 Damaged neighbourhoods covered by reconstruction plans⁦−21.9⁩%
K-1.2.1 Statistical bulletins and reports published (cumulative)⁦−20.0⁩%
K-6.2.1 Local projects delivered under governorate plans (cumulative)⁦−18.7⁩%
K-1.1.2 Savings from rationalised investment spending⁦−13.9⁩%
K-2.1.1 Infrastructure projects delivered to plan⁦−10.1⁩%
K-5.1.1 Citizen satisfaction with digital government services⁦−9.9⁩%
K-3.1.1 Hospital beds rehabilitated in public hospitals (cumulative)⁦−9.5⁩%
K-5.1.2 Government services fully available online⁦−9.0⁩%
K-5.2.3 Project data completeness & quality⁦−8.6⁩%
K-6.1.1 Transactions completed at citizen service centres per month⁦−4.3⁩%
K-2.1.2 Public facilities rehabilitated this year (cumulative)⁦−4.0⁩%
K-5.2.2 National PMO maturity index⁦−3.5⁩%
K-3.2.2 Employee engagement index at the Authority⁦−3.4⁩%
K-6.2.2 Share of investment spending in the least-developed governorates⁦−3.1⁩%
K-4.2.1 Grain reception centres rehabilitated⁦−2.3⁩%
K-4.1.1 Average time to pay wheat farmers⁦−1.8⁩%
Munjaz · RPT-17 · page ⁦3⁩ of ⁦7⁩Internal
Deviations & corrective actions report — October 2026 (latest)Planning and Statistics Authority

KPIs off the period target

KPIReadingTargetDeviationOwner
K-2.2.1 Damaged neighbourhoods covered by reconstruction plans4152.5⁦−21.9⁩%Eng. Qasem Al-Hariri
K-1.2.1 Statistical bulletins and reports published (cumulative)810⁦−20.0⁩%Dr. Firas Al-Obaid
K-6.2.1 Local projects delivered under governorate plans (cumulative)610750⁦−18.7⁩%Iman Al-Jasem
K-1.1.2 Savings from rationalised investment spending1.51.8⁦−13.9⁩%Rasha Al-Mudarres
K-2.1.1 Infrastructure projects delivered to plan7381.2⁦−10.1⁩%Eng. Wassim Al-Azm
K-5.1.1 Citizen satisfaction with digital government services7482.2⁦−9.9⁩%Eng. Lina Al-Attar
K-3.1.1 Hospital beds rehabilitated in public hospitals (cumulative)1,8102,000⁦−9.5⁩%Eng. Sara Al-Barazi
K-5.1.2 Government services fully available online6975.8⁦−9.0⁩%Basel Al-Mahayni
K-5.2.3 Project data completeness & quality8390.8⁦−8.6⁩%Nizar Abu Fakhr
K-6.1.1 Transactions completed at citizen service centres per month4.14.3⁦−4.3⁩%Ibrahim Al-Saeed
K-2.1.2 Public facilities rehabilitated this year (cumulative)4850⁦−4.0⁩%Eng. Qasem Al-Hariri
K-5.2.2 National PMO maturity index3.23.3⁦−3.5⁩%Dr. Reem Al-Qabbani
K-3.2.2 Employee engagement index at the Authority7173.5⁦−3.4⁩%Muhannad Al-Homsi
K-6.2.2 Share of investment spending in the least-developed governorates3132⁦−3.1⁩%Eng. Mustafa Al-Awa

Continued on the next page

Munjaz · RPT-17 · page ⁦4⁩ of ⁦7⁩Internal
Deviations & corrective actions report — October 2026 (latest)Planning and Statistics Authority

KPIs off the period target

KPIReadingTargetDeviationOwner
K-4.2.1 Grain reception centres rehabilitated8486⁦−2.3⁩%Eng. Bashir Al-Tai
K-4.1.1 Average time to pay wheat farmers9.59.3⁦−1.8⁩%Mariam Al-Zoubi
Munjaz · RPT-17 · page ⁦5⁩ of ⁦7⁩Internal
Deviations & corrective actions report — October 2026 (latest)Planning and Statistics Authority

Corrective actions

Corrective actionKPIOwnerDueStatus
Take the utility networks of the Darayya replacement housing out of the buildings contract and tender them separatelyK-2.1.1Eng. Qasem Al-Hariri⁦2026-11-30⁩In progress
Speed up the allocation of the Darayya site’s northern plot with Rif Dimashq Governorate and the electricity transmission & distribution establishmentK-2.1.1Eng. Wassim Al-Azm⁦2026-10-20⁩Overdue
An extra evening shift on the Aleppo substation bays until year endK-2.1.2Eng. Maher Al-Hamawi⁦2026-12-31⁩In progress
Fast-track three sector bulletins (prices, agriculture, industry) to publish them before year endK-1.2.1Dr. Firas Al-Obaid⁦2026-12-15⁩Open
Finish the four late grain reception centres in Hasakah before the next season planK-4.2.1Eng. Bashir Al-Tai⁦2026-11-15⁩In progress
Extend the hours of the Aleppo and Homs citizen service centres into the evening two days a weekK-6.1.1Ibrahim Al-Saeed⁦2026-10-25⁩Overdue
Rehabilitate two more pumping stations in the Suwayda water network within the current worksK-2.1.2Eng. Rami Youssef⁦2026-12-31⁩Open
Hand over the east-wing wards of Hama National Hospital in two batches instead of oneK-3.1.1Eng. Fadi Al-Droubi⁦2026-12-10⁩In progress
Link the medium-term plan tracker to governorate investment spending so spending counts as soon as it is bookedK-6.2.2Iman Al-Jasem⁦2026-11-20⁩Open
Workshops with the three governorate councils slowest in preparing damaged-neighbourhood plansK-2.2.1Iman Al-Jasem⁦2026-10-30⁩In progress
Adopt a quarterly schedule for local-project reports on the template the steering committee approvedK-6.2.1Eng. Mustafa Al-Awa⁦2026-11-25⁩Open
Link the grain reception centres to payment orders electronically to shorten farmer paymentsK-4.1.1Mariam Al-Zoubi⁦2026-11-05⁩In progress
Fix the five biggest complaints in the citizen journey on the unified e-services platform, starting with re-keyed civil-registry dataK-5.1.1Eng. Tarek Al-Mardini⁦2026-11-30⁩In progress
Speed up the civil-registry integration in the unified e-services platform with a dedicated integration squadK-5.1.1Hamza Al-Hussein⁦2026-10-22⁩Overdue
Ship 6 priority e-services before year end in an interim releaseK-5.1.2Basel Al-Mahayni⁦2026-12-20⁩Open
Contract two engineering design offices to clear the backlog of neighbourhood plansK-2.2.1Iman Al-Jasem⁦2026-11-10⁩In progress

Continued on the next page

Munjaz · RPT-17 · page ⁦6⁩ of ⁦7⁩Internal
Deviations & corrective actions report — October 2026 (latest)Planning and Statistics Authority

Corrective actions

Corrective actionKPIOwnerDueStatus
Require the governorate planning directorates to log neighbourhood field-survey results within 48 hoursK-2.2.1Eng. Mustafa Al-Awa⁦2026-12-31⁩Open
An improvement plan for the benefits dimension of the maturity modelK-5.2.2Dr. Reem Al-Qabbani⁦2026-12-15⁩Open
Turn on automatic reminders and escalate projects not updated within 7 daysK-5.2.3Nizar Abu Fakhr⁦2026-11-01⁩In progress
A Munjaz data-update workshop for the ministries’ construction project managersK-5.2.3Dr. Reem Al-Qabbani⁦2026-10-15⁩Completed
Pool the purchase of transformers and cables for the energy projects through the General Authority for Supply and ProvisionK-1.1.2Rasha Al-Mudarres⁦2026-11-30⁩Open
An action plan per directorate from the engagement surveyK-3.2.2Muhannad Al-Homsi⁦2026-12-31⁩Open
Munjaz · RPT-17 · page ⁦7⁩ of ⁦7⁩Internal