Authority report to the national steering committee — Q3 2026

National Steering Committee or Executive Council reportConfidential

Planning and Statistics Authority · Q3 2026

Shown by your permissionsProject Management Office: 36 projects — everything in your scope

Planning and Statistics AuthorityMunjazStrategy & projectsMunjazPMO PLATFORM

National Steering Committee or Executive Council report

Authority report to the national steering committee — Q3 2026

Planning and Statistics Authority

Period
Q3 2026
Generated
15 October 2026
Submitted to
The National Projects Steering Committee and the Authority’s Executive Council
Owner
Dr. Ziad Al-Atassi

Prepared by the National PMO — automatically, on Munjaz

Munjaz · RPT-09 · page ⁦1⁩ of ⁦5⁩Confidential
Authority report to the national steering committee — Q3 2026Planning and Statistics Authority

Executive summary

Written by Copilot from system data — review before sending

The scope holds 36 projects with a budget of SYP 129.28bn: 18 on track and 6 red or critical. Weighted progress is 52% against 57% planned, spend SYP 60.34bn, and EAC SYP 139.48bn (SYP 10.19bn over).

12 projects are more than a month behind baseline; the worst: Hama National Hospital Upgrade & Extension (152 days), Aleppo 230 kV Substations Rehabilitation (126 days), Sheikh Najjar Industrial City Rehabilitation (95 days).

18 high risks are open with SYP 10.08bn of exposure; the decisions needed centre on reconstruction contractor distress and the large change requests.

Key figures

Projects
36
Budget
SYP 129.3B
Spent
SYP 60.3B
EAC
SYP 139.5B
Progress
⁦52%⁩ / ⁦57%⁩
SPI
0.85
CPI
0.93
High risks
18

Project health mix

  • On track 18
  • At risk 10
  • Off track 4
  • Critical 2
  • On hold 2
Munjaz · RPT-09 · page ⁦2⁩ of ⁦5⁩Confidential
Authority report to the national steering committee — Q3 2026Planning and Statistics Authority

Strategic objectives

ObjectiveAchievedTarget
SO-1.1Stimulate growth, restore production and attract investment⁦83%⁩⁦90%⁩
SO-1.2Reliable statistics and economic data for decisions⁦69%⁩⁦80%⁩
SO-2.1Rehabilitate core energy, water and transport infrastructure⁦74%⁩⁦85%⁩
SO-2.2Rebuild damaged areas and provide replacement housing⁦66%⁩⁦80%⁩
SO-3.1Better access to health and education⁦76%⁩⁦85%⁩
SO-3.2Develop human capital in public bodies⁦82%⁩⁦85%⁩
SO-4.1Strengthen food security and revive wheat farming⁦79%⁩⁦85%⁩
SO-4.2Develop rural areas and spur agricultural investment⁦88%⁩⁦90%⁩
SO-5.1Integrated digital government services for citizens⁦72%⁩⁦85%⁩
SO-5.2Sound governance and effective follow-up of projects and data⁦85%⁩⁦90%⁩
SO-6.1Comparable public-service quality in every governorate⁦77%⁩⁦80%⁩
SO-6.2Governorate plans and a balanced share of public investment⁦70%⁩⁦80%⁩
Munjaz · RPT-09 · page ⁦3⁩ of ⁦5⁩Confidential
Authority report to the national steering committee — Q3 2026Planning and Statistics Authority

Projects with the most at stake

ProjectSectorBudgetProgressHealth
Darayya Replacement HousingProjects Follow-upSYP 29.5B⁦42%⁩Off track
Hama National Hospital Upgrade & ExtensionProjects Follow-upSYP 16B⁦57%⁩Critical
Deir ez-Zor Suspension Bridge ReconstructionProjects Follow-upSYP 13B⁦2%⁩On track
Aleppo 230 kV Substations RehabilitationProjects Follow-upSYP 10.3B⁦68%⁩Critical
Douma Wastewater Treatment PlantProjects Follow-upSYP 8.6B⁦44%⁩Off track
Sheikh Najjar Industrial City RehabilitationLocal DevelopmentSYP 7.2B⁦39%⁩Off track
Maarat al-Numan Infrastructure Rehabilitation — with Idlib GovernorateProjects Follow-upSYP 6B⁦33%⁩At risk
Al-Mayadin General HospitalProjects Follow-upSYP 5.3B⁦2%⁩On hold
Latakia University Technical Engineering Faculty ExtensionProjects Follow-upSYP 4B⁦52%⁩At risk
Government Backup Data Centre, Homs — Phase 2DigitalSYP 3.7B⁦72%⁩At risk
Government Fibre Backbone — Damascus–Homs SegmentDigitalSYP 3.3B⁦55%⁩At risk
Unified Government Contact Centre & AI AssistantDigitalSYP 2.8B⁦0%⁩On track

The largest ⁦12⁩ of ⁦36⁩ by budget — the full table is in the Excel file

Munjaz · RPT-09 · page ⁦4⁩ of ⁦5⁩Confidential
Authority report to the national steering committee — Q3 2026Planning and Statistics Authority

Highest-exposure risks

RiskScoreExposure
Main contractor cash-flow trouble and late payment of subcontractorsAleppo 230 kV Substations Rehabilitation25SYP 900M
Steel and concrete price rises driving price-adjustment claimsDarayya Replacement Housing20SYP 1.2B
Contractor’s financial claims piling up over unapproved change ordersHama National Hospital Upgrade & Extension20SYP 1B
Late hand-over of the northern plot and utility diversions in blocks 3 and 4Darayya Replacement Housing20SYP 775M
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16Douma Wastewater Treatment Plant20SYP 675M
Late land allocation and registration by the Deir ez-Zor governorate councilAl-Mayadin General Hospital20SYP 300M
Ground-improvement costs up after the geotechnical surveySheikh Najjar Industrial City Rehabilitation16SYP 562.5M

Decisions needed

  1. 1

    Pay subcontractors directly on the Aleppo 230 kV substations rehabilitation

    The National PMO recommends paying directly out of certificate 22 and deducting it from the main contractor’s dues.

  2. 2

    Refer the Hama National Hospital contractor’s claims to arbitration

    Legal Affairs recommends referral, with an independent engineer assessing the extension request in parallel.

  3. 3

    Approve the updated corrective plan for the Unified Government e-Services Platform

    The National Steering Committee recommends conditional approval with a monthly progress review.

  4. 4

    Release SYP 550M of the Reconstruction & Infrastructure portfolio reserve to speed up the Darayya housing land hand-over

    The Infrastructure & Reconstruction Projects directorate recommends two tranches tied to site hand-overs.